On Approval of the Concept for the Development of the Water Resources Management System of the Republic of Kazakhstan for 2024–2030

АMANAT партиясы және Заң және Құқық адвокаттық кеңсесінің серіктестігі аясында елге тегін заң көмегі көрсетілді

On Approval of the Concept for the Development of the Water Resources Management System of the Republic of Kazakhstan for 2024–2030

Resolution of the Government of the Republic of Kazakhstan dated February 5, 2024 No. 66.

The Government of the Republic of Kazakhstan HEREBY RESOLVES:

1. To approve the attached Concept for the Development of the Water Resources Management System of the Republic of Kazakhstan for 2024–2030 (hereinafter referred to as the Concept).

2. The central and local executive bodies, state bodies directly subordinate and accountable to the President of the Republic of Kazakhstan (upon agreement), and other organizations (upon agreement), responsible for the implementation of the Concept, shall:

1) take the necessary measures to implement the Concept;

2) submit information on the progress of implementation of the Concept in accordance with the procedure and within the time limits established by Resolution of the Government of the Republic of Kazakhstan dated November 29, 2017 No. 790 "On Approval of the State Planning System in the Republic of Kazakhstan".

3. Control over the implementation of this Resolution shall be entrusted to the Ministry of Water Resources and Irrigation of the Republic of Kazakhstan.

4. This Resolution shall enter into force on the date of its signing.

Prime Minister of the Republic of KazakhstanA. Smailov

| | Approved by the Resolution of the Government of the Republic of Kazakhstan dated February 5, 2024 No. 66 || - | ------------------------------------------------------------------------------------------------------- |

Concept for the Development of the Water Resources Management System of the Republic of Kazakhstan for 2024–2030

Footnote. The Concept is presented in the wording of Resolution of the Government of the Republic of Kazakhstan dated 28.08.2024 No. 695.

Contents

Section 1. Passport (key parameters)

Section 2. Analysis of the current situation

Section 3. Review of international experience

Section 4. Vision for the development of the water sector

Section 5. Basic principles and approaches to the development of the water sector

Section 6. Target indicators and expected results

Section 7. Action Plan for the implementation of the Concept for the Development of the Water Resources Management System of the Republic of Kazakhstan for 2024–2030 (Appendix to the Concept)

Section 1. Passport (key parameters)

Download

NameConcept for the Development of the Water Resources Management System of the Republic of Kazakhstan for 2024–2030
Grounds for development1. Decree of the President of the Republic of Kazakhstan dated September 13, 2022 No. 1008 "On Measures to Implement the Address of the Head of State to the People of Kazakhstan dated September 1, 2022, 'A Fair State. One Nation. A Prosperous Society'". 2. Decree of the President of the Republic of Kazakhstan dated November 26, 2022 No. 2 "On Measures to Implement the Election Programme of the President of the Republic of Kazakhstan 'Fair Kazakhstan for All and for Everyone. Now and Forever'". 3. Minutes of the meeting on the flood situation chaired by the President of the Republic of Kazakhstan dated April 1, 2024 No. 24-01-7.4 (paragraph 2.4). 4. Minutes of the meeting on the presentation of draft concepts for the development of sectors/areas chaired by the Prime Minister of the Republic of Kazakhstan A.A. Smailov dated February 20, 2023 No. 12-03/07-1230. 5. Minutes of the meeting of the Water Council of Kazakhstan chaired by the Prime Minister of the Republic of Kazakhstan A.A. Smailov dated October 18, 2022 No. 17-03/07-1183. 6. Instruction of the Prime Minister of the Republic of Kazakhstan dated September 21, 2022 No. 17-07/4652//22-4596, 4619, on the implementation of the instruction of the Accounts Committee for Control over Execution of the Republican Budget dated August 11, 2022 No. 20-1-N "On the Results of the State Audit of the Implementation of Measures to Ensure the Supply of Water to the Southern Region".
State body responsible for developmentMinistry of Water Resources and Irrigation of the Republic of Kazakhstan
State bodies and organizations responsible for implementationMinistry of Water Resources and Irrigation of the Republic of Kazakhstan; Ministry of Agriculture of the Republic of Kazakhstan; Ministry of Ecology and Natural Resources of the Republic of Kazakhstan; Ministry of Foreign Affairs of the Republic of Kazakhstan; Ministry of Emergency Situations of the Republic of Kazakhstan; Ministry of Digital Development, Innovation and Aerospace Industry of the Republic of Kazakhstan; Ministry of Energy of the Republic of Kazakhstan; Ministry of Science and Higher Education of the Republic of Kazakhstan; Ministry of Industry and Construction of the Republic of Kazakhstan; Ministry of Healthcare of the Republic of Kazakhstan; Ministry of Finance of the Republic of Kazakhstan; Ministry of Education of the Republic of Kazakhstan; Ministry of Defence of the Republic of Kazakhstan; Ministry of Internal Affairs of the Republic of Kazakhstan; National Security Committee of the Republic of Kazakhstan; Agency for Protection and Development of Competition of the Republic of Kazakhstan; Academy of Public Administration under the President of the Republic of Kazakhstan; akimats of the regions and the cities of Astana, Almaty and Shymkent; non-commercial joint-stock company "National Hydrogeological Service "Kazhydrogeology"; republican state enterprise on the right of economic management "Kazvodkhoz"; republican state enterprise "Kazhydromet"; joint-stock company "National Company "Қазақстан Ғарыш Сапары"; limited liability partnership "Kazakh Scientific Research Institute of Water Management"; organizations of higher and postgraduate education
Implementation period2024–2030

Section 2. Analysis of the current situation

2.1. Assessment of the current state of water resources

Effective water resources management is a key factor in ensuring the country's sustainable socio-economic development, as well as water, food and energy security, by maintaining a water balance to meet the water needs of all water users and water consumers.

At the same time, current consumption and use of water resources are often unsustainable and irrational, resulting in their excessive use, pollution and depletion.

The situation is exacerbated by the impact of global climate change, which leads to droughts and floods, deterioration in water quality and reduced availability of safe drinking water.

In the context of increasing pressure on water resources and the growing intensity of extreme climate-related events, improving the water resources management system is of key importance in addressing existing infrastructure, institutional, financial and other problematic issues.

2.1.1. Surface water resources

According to the hydrographic principle, the country's territory is divided into 8 water management basins: Aral-Syr Darya, Balkhash-Alakol, Irtysh, Ishim, Zhaiyk-Caspian, Nura-Sarysu, Tobol-Torgai and Shu-Talas.

The main volume of water resources is provided by surface waters, with an average long-term volume of 106 km3, of which 55.7% is formed within the country's territory, while the remaining 44.3% is provided by the inflow of transboundary rivers from China, Uzbekistan, Russia and Kyrgyzstan. This significantly increases the importance of regulating transboundary water flows in addressing existing and potential water-related problems in the country (see Table 1).

Table 1. Average long-term river flow resources¹, km³

Download

No.Water management basinsLocal resourcesInflow from outside the countryTotal resources³Outflow beyond the country's borders   
totalformed in the territory of neighbouring countries²totalnon-returnablereturnable    
123456789
1Aral-Syr Darya3.2016.916.519.70.38 0.38
2Balkhash-Alakol18.513.512.531.00.96 0.96
3Irtysh26.88.326.9633.825.123.71.36
4Ishim2.81  2.811.801.80 
5Zhaiyk-Caspian⁴3.398.867.8711.30.99 0.99
6Nura-Sarysu⁵1.30  1.30   
7Tobol-Torgai1.820.450.452.270.490.49 
8Shu-Talas⁶1.442.772.774.21   
 Total for the Republic of Kazakhstan59.350.847.110629.726.03.70

Notes:

¹ According to data from the joint-stock company "Institute of Geography and Water Security".

² The inflow from outside the country, formed in the territory of neighbouring countries, indicated in column 5, excludes return flow formed within the territory of Kazakhstan.

³ The total average long-term river flow resources indicated in column 6 include local resources and inflow formed in the territory of neighbouring countries ([6]=[3]+[5]).

⁴ The inflow into the Zhaiyk-Caspian water management basin is indicated without taking into account the inflow through the Kigash and Sharovka branches of the Volga River.

⁵ The total average long-term river flow resources in column 6 of the Nura-Sarysu water management basin are indicated without taking into account the water transferred from the Irtysh water management basin through the K.I. Satpayev Canal in the amount of 0.70 km³.

⁶ The inflow into the Shu-Talas water management basin is indicated without taking into account the inflow through canals from the territory of the Kyrgyz Republic.

As of March 1, 2023, the average long-term river flow in the territory of Kazakhstan had decreased by 12.5 km3 compared with 1960, of which 9.0 km3, or 72% of the total reduction, accounted for local rivers, while transboundary rivers accounted for 3.5 km3, or 28%. The reduction in the flow of local rivers occurred in all basins except the Balkhash-Alakol and Tobol-Torgai basins.

Water resources are unevenly distributed throughout the country's territory; therefore, the situation regarding the availability of surface water resources differs significantly across individual regions of the republic.

The south-eastern and eastern regions of the country (the Irtysh and Balkhash-Alakol water management basins) are the most adequately supplied with their own surface water resources. The central region (the Nura-Sarysu water management basin) is the least adequately supplied.

The southern, south-eastern and western regions of the country (the Aral-Syr Darya, Balkhash-Alakol, Shu-Talas and Zhaiyk-Caspian water management basins) are the most dependent on water inflows from the territories of neighbouring countries.

2.1.2. Groundwater resources

The use of groundwater is a particularly acute issue in Kazakhstan. According to 2023 data, there are 4,416 deposits (5,384 sites) with approved groundwater reserves amounting to 43,120.56 thousand m3/day within the country's territory, including the following categories:

Category A (developed) – 13,428.23 thousand m3/day;

Category B (explored) – 13,481.26 thousand m3/day;

Category C1 (preliminarily assessed) – 10,675.31 thousand m3/day;

Category C2 (identified) – 5,535.75 thousand m3/day.

Forecast reserves amount to approximately 40 km3/year.

According to their intended purpose, operational reserves are divided as follows:

1) for domestic and drinking water supply (hereinafter referred to as DDWS) – 13,882.66 thousand m3/day (3,692 deposits, 4,288 sites);

2) for industrial and technical water supply (hereinafter referred to as ITWS), including drainage water – 1,932.6 thousand m3/day (377 deposits, 407 sites);

3) for land irrigation (hereinafter referred to as LI) – 17,384.91 thousand m3/day (155 deposits, 287 sites);

4) for DDWS and ITWS – 3,047.23 thousand m3/day (164 deposits, 314 sites);

5) for DDWS and LI – 4,951.94 thousand m3/day (18 deposits, 78 sites);

6) for DDWS, ITWS and LI – 725.0 thousand m3/day (1 deposit);

7) for DDWS, LI and reserves for compensating damage to spring flow – 1,109.7 thousand m3/day (1 deposit, 3 sites).

The distribution of groundwater resources throughout the territory of Kazakhstan is extremely uneven. Approximately 68% of groundwater resources with a mineralization level of up to 1 g/l are concentrated in the southern region: Almaty, Zhambyl, Turkistan and Kyzylorda regions.

Aktobe Region is reliably supplied with groundwater reserves for domestic and drinking water supply. West Kazakhstan, Kostanay and Akmola regions are partially supplied, while Atyrau, Mangystau and North Kazakhstan regions are insufficiently supplied.

During the period from 1960 to 2020, hydrogeological surveys were conducted throughout the territory of Kazakhstan, with the development of maps at a scale of 1:200,000. However, up-to-date data on groundwater reserves, the distribution areas of aquifers, their thickness and the coordinates of deposits by regions and river basins are currently unavailable.

2.1.3. Use of water resources

Water abstraction for the needs of economic sectors and the population amounted to 24.9 km3 in 2020, 24.5 km3 in 2021, 25.0 km3 in 2022 and 24.9 km3 in 2023. This trend is stable, but an increase in water abstraction is possible due to the acceleration of development in the oil and gas sector in the west of the country and the mining sector in central Kazakhstan.

Industry accounts for 23.5% of total water abstraction, of which 94.7% is supplied from surface sources and 5.3% from groundwater. Of the total volume of water abstracted by industry, 75% is discharged into water bodies after regulatory treatment.

Agriculture accounts for 60% of total water abstraction. On average, from 2020 to 2022, water abstraction for agricultural needs amounted to 14.8 km3, of which 77% was used for regular irrigation over an area of 1.18 million hectares, while the remaining 3.61 km3 was distributed among flood irrigation, the flooding of hayfields, agricultural water supply and pasture watering. Water abstraction was carried out from surface sources in 98.8% of cases.

At the same time, since 2020, agriculture has seen a decrease in the volume of water abstraction for irrigation and irrigated land, while the ratio of losses to water abstraction has remained virtually unchanged.

Table 2. Dynamics of water abstraction for regular irrigation by water management basins of the Republic of Kazakhstan

Download

No.Water management basins2020  2021  2022  2023  
  Irrigated land, thousand haWater abstraction, million m3Specific consumption, thousand m3/haIrrigated land, thousand haWater abstraction, million m3Specific consumption, thousand m3/haIrrigated land, thousand haWater abstraction, million m3Specific consumption, thousand m3/haIrrigated land, thousand haWater abstraction, million m3Specific consumption, thousand m3/ha
1Aral-Syr Darya6427,45611.65366,92012.95906,78111.56947,12610.2
2Balkhash-Alakol4563,4017.54533,3107.33123,34710.72913,22911.1
3Irtysh491653.4481583.3521743.3631872.96
4Ishim6101.89141.5850.612110.92
5Zhaiyk-Caspian12463.912484.115473.213483.69
6Nura-Sarysu24743.19747.920743.725923.68
7Tobol-Torgai6132.27132.08202.38212.63
8Shu-Talas8493611.21049369.01391,0407.51221,0028.21
 Total:1,27712,1019.51,17712,10110.31,14411,48910.01,22811,9059.69

Note: according to reports of the basin inspectorates for the regulation of the use and protection of water resources of the Water Resources Committee of the Ministry of Water Resources and Irrigation of the Republic of Kazakhstan.

The largest agricultural consumer of water resources is regular irrigation, which has seen a negative trend of increasing specific water consumption rates from 8.5 m3/ha in 2011 to 10 m3/ha in 2022. According to the assessment of the LLP "Kazakh Scientific Research Institute of Water Management" (hereinafter referred to as LLP "KazNIIVH"), this is associated with climate change, which affects the increase in water consumption standards for agricultural crops. Thus, the average number of irrigation cycles during the growing season has increased from 5 to 6.

At present, the average rate of introduction of water-saving irrigation technologies is 30.0 thousand hectares per year, compared with the minimum required level of 150 thousand hectares per year (see Figure 1).

Figure 1. Dynamics of the introduction of water-saving irrigation technologies in the Republic of Kazakhstan

image

Note: according to data from LLP "KazNIIVH".

An imbalance in anthropogenic pressure on water resources and the resulting water deficit are observed across the main river basins.

An analysis of the level of anthropogenic pressure on rivers indicates the following. The Nura-Sarysu water management basin is characterized by critically high pressure on water resources. The available water resources, 88% of which are used for production purposes, are fully involved in economic circulation, and the future socio-economic development of central Kazakhstan will depend on the safe operation of the Kanysh Satpayev Canal, which supplies the basin with water from the Irtysh River.

Very high pressure on water resources is observed in the Aral-Syr Darya and Shu-Talas water management basins. In addition, almost 90% of the river flow resources in the Aral-Syr Darya water management basin originate from neighbouring countries of Central Asia, while 75% of the river flow in the Shu-Talas water management basin is formed in the territory of Kyrgyzstan.

Available water resources do not cover the needs of the population and economic sectors, which is a critical factor for the further socio-economic development of Turkistan, Kyzylorda and Zhambyl regions.

In the Aral-Syr Darya water management basin, the share of water abstraction for agricultural needs is 98%, since more than 35% of the country's irrigated land is located in this basin (Turkistan and Kyzylorda regions). The most water-intensive agricultural crops, such as rice and cotton, are cultivated on these lands. On average, losses during the supply of water for regular irrigation of agricultural crops amount to 1.7 km3 of the total water abstraction.

In the Shu-Talas water management basin, 97% of total water abstraction is used for irrigation, with water transportation losses averaging 0.6 km3 of the total water abstraction.

In the Ishim water management basin, there is high pressure on local water resources, 96% of which are used for domestic and household needs.

Water supply to the city of Astana is also an acute problem, caused by the continuous growth of the city's population. Until 2020, water consumption by residents of the capital amounted to 269 thousand m3 per day; since 2022, it has amounted to 311 thousand m3 per day. According to forecasts, due to the active construction of residential neighbourhoods in the city, water consumption will reach 340 thousand m3 per day by 2026.

Today, the capital's water supply is provided by a single source – the Astana Reservoir, built in 1969 and designed for a population of 500 thousand people. Due to the growth of the city's population (1.3 million people), the need to create a reserve source of drinking water for the city of Astana is becoming increasingly urgent.

In the Zhaiyk-Caspian water management basin, moderate pressure on water resources is observed. At the same time, the limiting factor is that 71% of the river flow originates in Russia. The main problems of the basin are the depletion (shallowness) and pollution of the Zhaiyk River due to the regulation of the river and the discharge of pollutants from the territory of Russia.

Moderate pressure on water resources is observed in the Balkhash-Alakol and Irtysh river water management basins, while low pressure is observed in the Tobol-Torgai basin. Accordingly, these river water management basins have sufficient water resource potential for further socio-economic development, provided that water inflows from neighbouring countries are maintained.

In the Balkhash-Alakol water management basin, 83% of total water abstraction is used in agriculture, where losses amount to 1.0 km3 of the total water abstraction.

In the Irtysh water management basin, the priority measure is to improve the water quality of the Irtysh River, which at this stage serves as a source for supplying industrial and domestic drinking water needs in central Kazakhstan. Due to the operation of the Bukhtarma and Shulba reservoirs in hydropower mode, there are problems with flooding the Irtysh River floodplain during the spring high-water period.

The available river flow resources of the Tobol-Torgai basin amount to 2.1 km3, of which 29% of the flow is formed in the territory of Russia. In the Tobol-Torgai river water management basin, water losses in water supply systems amount to 20%.

An analysis of the water management situation across river water management basins shows that it is not possible to rely on the available free river flow resources due to the extremely uneven distribution of river water resources throughout the country's territory. This leads to instability and unevenness in the water supply of water management basins and economic sectors.

According to preliminary forecasts, the water management balance up to 2030 indicates a reduction in internal river flow resources from 106 km3 to 104 km3 due to a decrease in inflows from the territories of neighbouring countries from 50.8 km3 to 46.4 km3 (see Table 3), while an increase in locally generated resources is expected.

Table 3. Forecast values of river flow resources of the Republic of Kazakhstan, taking into account climate and anthropogenic pressures by 2030¹, km³

Download

| No. | Water management basins | Local resources | Inflow from outside the country | Total resources³ | Outflow beyond the country's borders | | | ||---|---|---|---|---|---|---|| total | formed in the territory of neighbouring countries² | total | non-returnable | returnable | | | | || 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 || 1 | Aral-Syr Darya | 4.01 | 14.4 | 13.9 | 17.9 | 0.48 | | 0.48 || 2 | Balkhash-Alakol | 19.2 | 12.5 | 11.5 | 30.7 | 0.99 | | 0.99 || 3 | Irtysh | 27.1 | 7.13 | 5.82 | 32.9 | 22.9 | 21.6 | 1.31 || 4 | Ishim | 2.61 | | | 2.61 | 1.47 | 1.47 | || 5 | Zhaiyk-Caspian⁴ | 3.33 | 8.63 | 7.66 | 11.0 | 0.97 | | 0.97 || 6 | Nura-Sarysu⁵ | 1.91 | | | 1.91 | | | || 7 | Tobol-Torgai | 2.03 | 0.59 | 0.59 | 2.62 | 0.98 | 0.98 | || 8 | Shu-Talas⁶ | 1.54 | 3.21 | 3.21 | 4.75 | | | || | Total for the Republic of Kazakhstan | 61.7 | 46.4 | 42.7 | 104 | 27.8 | 24.0 | 3.75 |

Notes:

1 According to data from the joint-stock company "Institute of Geography and Water Security".

² The inflow from outside the country, formed in the territory of neighbouring countries, indicated in column 5, excludes return flow formed within the territory of Kazakhstan.

³ The total average long-term river flow resources indicated in column 6 include local resources (column 3) and inflow formed in the territory of neighbouring countries (column 6).

⁴ The inflow into the Zhaiyk-Caspian water management basin is indicated without taking into account the inflow through the Volga River branches – Kigash and Sharovka.

⁵ The total average long-term river flow resources in column 6 of the Nura-Sarysu water management basin are indicated without taking into account the water transferred from the Irtysh water management basin through the K.I. Satpayev Canal in the amount of 0.70 km³.

⁶ The inflow into the Shu-Talas water management basin is indicated without taking into account the inflow through canals from the territory of the Kyrgyz Republic.

The increase in local resources is occurring due to the accelerated rate of glacier melting. However, as the area of glaciers decreases, this flow will also decline.

In the future, a significant increase in the country's population, livestock numbers, volumes of aquaculture production and industrial output is expected, which will lead to an increase in water abstraction for these needs.

The main causes of inefficient use of water resources include the application of outdated water-intensive technologies in production, significant water losses during transportation through earthen canals, insufficient equipment of water intake facilities with water metering systems, as well as the absence of effective economic mechanisms to encourage enterprises to introduce advanced water-saving technologies, closed-loop and recycled water supply systems, and reduce non-productive water losses.

In addition, more efficient use of groundwater is hindered by the following aspects:

low level of development of operational groundwater reserves, as well as use of the potential of geothermal waters;

absence of re-approved groundwater reserve data for irrigation purposes;

non-use of approximately 90% of approved groundwater reserves;

extraction of a significant share of groundwater at subsurface sites without approved groundwater reserves;

depletion of groundwater deposits due to violations of their use regime, as well as excessive extraction from the unallocated subsurface resources fund;

pollution of groundwater deposits as a result of intensive subsurface use. For example, in Turkistan Region, wells in the Sozak District are being contaminated with sulfuric acid during its injection into underground uranium deposits and become unusable.

2.2. Main problems of the water sector requiring resolution in the medium term

2.2.1. Irrational and inefficient use of water resources

1. Inefficient use of water resources in agriculture

Against the background of forecast reductions in river flow resources (transboundary and local), there is a problem of wasteful water use, particularly in agriculture.

Particularly low water productivity is observed in agriculture due to the deterioration of the technical condition of irrigated land infrastructure. As a result, the water use efficiency coefficient in delivering water to irrigated fields has decreased from 0.8 to 0.5–0.55 over the past 30 years.

At the same time, the main share of water abstraction (60%) is accounted for by agriculture. Of the volume of water consumed by agriculture, the main share is attributable to regular irrigation (10.6 km3 in 2009 and 11.2 km3 in 2022), where losses also increase as water abstraction grows (2 km3 in 2009 and 2.2 km3 in 2022). This indicates that water transportation losses in irrigated agriculture have decreased by 15% since 2009 as a result of ongoing efforts to modernize water infrastructure. Nevertheless, as of the end of 2022, the share of losses in irrigated agriculture remains high, amounting to 65%.

At the same time, in the southern regions of the country, where the main share of irrigated agriculture is concentrated, the level of introduction of water-saving technologies amounts to only 3% of the total area of irrigated land.

There is a low level of use of treated domestic and industrial wastewater in irrigated agriculture, which is due to the absence of a methodology for its application.

If the current situation regarding the use of water resources by economic sectors and the population persists, there is a risk of a slowdown in socio-economic development by 2029 due to water shortages.

2. Lack of proper accounting and control over the use of water resources

Water accounting in irrigated agriculture is organized at a low level. Water delivery points for farms are not equipped with reliable and accurate metering devices.

Water measurement is carried out using outdated methods, and not all devices undergo proper calibration and certification. This leads to reduced accuracy in water accounting and inflated service costs, which may create problems in planning and optimizing the use of water resources.

In addition, mass production of water meters has not been established in the republic, which could contribute to their rapid installation among all water users, improving accounting accuracy and collection of payments for irrigation water.

Furthermore, insufficient control over large-scale mineral extraction in riverbeds leads to the drying up of small rivers and their tributaries. This problem is particularly relevant in Almaty, Zhambyl and Turkistan regions and the Zhetysu Region. The development of subsurface resources in riverbeds and foothill areas leads to the disappearance of small rivers, which negatively affects the formation of groundwater and surface water. There are also cases of illegal removal of sand and gravel mixtures by individuals and legal entities from water management facilities of republican significance. At the same time, illegal quarries are being formed along canal beds, causing damage to the water management facility by compromising its structural components.

The balance sheet of the republican state enterprise on the right of economic management "Kazvodkhoz" (hereinafter referred to as RSE on the REM "Kazvodkhoz") includes large reservoirs (Shardara, Astana, Sergeevka, Kengir, Karatomar, etc.) and the Koksarai Counter-Regulator, which have become popular recreational areas. At the same time, many water bodies lack basic conditions for comfortable and safe recreation. Water legislation of the Republic of Kazakhstan provides for the possibility of using water bodies for health and recreational purposes without a special permit, except for water bodies that pose a potential mudflow hazard. However, the limited scope of statutory activities does not allow RSE on the REM "Kazvodkhoz" to use the available recreational resources to improve the existing conditions at these facilities.

2.2.2. Outdated water infrastructure

1. Inadequate technical condition of water infrastructure

Regular technical maintenance and monitoring of the condition of facilities, scheduled and emergency repairs, as well as modernization and technical improvement of existing systems to increase their efficiency and reliability are of decisive importance for ensuring uninterrupted and safe water supply to water users.

Kazakhstan's water management complex includes 405 reservoirs with a design capacity of 87.8 km3, 118 hydraulic units, 8,577 canals, 461 dams and 3,805 other structures, including 1,502 retaining structures, which require regular inspection.

The actual deterioration of water management systems and structures averages more than 70% across the republic. Many water management facilities have been operated without major repairs or reconstruction for more than 30–50 years, making them high-risk facilities.

In general, due to the inadequate technical condition of water infrastructure, average water losses during transportation through main canals from 2020 to 2023 amounted to 20% of the water abstracted. Taking into account losses in inter-farm and on-farm canals in the fields, losses exceed 50%. For comparison: water transportation losses amount to 5% in Singapore, 7% in Japan, 6% in the Netherlands and 19% in France.

2. Incomplete coverage of water management systems and structures by comprehensive surveys

Currently, the Ministry of Water Resources and Irrigation of the Republic of Kazakhstan maintains centralized records of repair works only for republican facilities.

As a result, municipal and private facilities remain unattended, despite the fact that the largest accidents have occurred at such facilities – the collapse of the Kyzylagash dam (2010, Zhetysu Region) and the Kokpekty dam (2014, Karaganda Region), which resulted in the deaths of 50 people.

These emergencies demonstrate the need for systematic monitoring and ensuring the safety of hydraulic structures, as well as improving the regulatory framework.

However, at present, water users do not ensure the proper maintenance of water bodies during their operation, since agreements on special water use grant tenants only the right to use the water surface, while the maintenance of hydraulic structures remains the responsibility of local executive bodies.

At the same time, according to the water legislation of the Republic of Kazakhstan, water users are obliged to maintain water management structures and technical devices in proper working condition.

According to the requirements of water legislation, owners of hydraulic structures conduct comprehensive surveys, which make it possible to determine the instrumental condition of hydraulic structures and declare their safety: for water management systems and structures that have been in operation for more than 25 years – annually, and for those in operation for up to 25 years – once every 5 years.

The purposes of comprehensive surveys (integrated assessments) of hydraulic structures are to assess the actual technical condition of hydraulic structures and their main equipment, determine the remaining service life of their components, and establish the safety deficit in order to assess the possibility of continuing to operate hydraulic structures beyond their designated service life (or the 25-year period). The results of comprehensive surveys of hydraulic structures serve as the basis for preparing hydraulic structures for an extension of their service life.

At the same time, the practice of previous years shows that the surveys of hydraulic structures conducted in Kazakhstan do not fully cover the entire range of issues relating to the overall condition of hydraulic structures and do not provide an objective assessment of their actual condition.

As of February 1, 2024, comprehensive surveys had been conducted at 118 out of 1,502 hydraulic structures (8% of the total), of which 32 structures are in republican ownership, 79 in municipal ownership and 7 in private ownership.

Annual visual inspections of all 1,502 hydraulic structures (reservoirs – 405, dams – 247, embankment dams – 461, hydraulic units – 118, ponds – 271), including 331 in republican ownership, 936 in municipal ownership, 229 in private ownership and 6 ownerless facilities, were conducted by specialists of basin inspectorates jointly with the Departments of Emergency Situations, local executive bodies and the owners of hydraulic structures. Based on the results, 537 structures require repairs (52 in republican ownership, 427 in municipal ownership, 49 in private ownership and 9 ownerless facilities).

According to the Ministry of Water Resources and Irrigation of the Republic of Kazakhstan, hydraulic structures requiring repairs are located in Karaganda Region – 203, East Kazakhstan Region – 54, Almaty Region – 48, Aktobe Region – 29, Abai Region – 28, Akmola Region – 27, Zhambyl Region – 18, West Kazakhstan Region – 15, Ulytau Region – 15, Zhetysu Region – 13, Kostanay Region – 12, Kyzylorda Region – 11, Turkistan Region – 11, Atyrau Region – 7, North Kazakhstan Region – 5, Pavlodar Region – 3 and Mangystau Region – 1, in the city of Almaty – 9 and in the city of Shymkent – 1.

2.2.3. Lack of adequate information and analytical support and monitoring of the water resources management system

The key role in the use and protection of water resources belongs to state monitoring of water bodies, which is aimed at the timely identification and forecasting of negative processes affecting the quality and condition of water bodies, the development and implementation of measures to prevent these processes, as well as the assessment of the effectiveness of water body protection measures.

There are reservoirs in the country that pose a potential threat to the population in the event of their collapse, which, in turn, do not have local warning systems or have such systems in an inoperative condition. This system is necessary to inform citizens living in settlements located within the calculated zone of potential emergency impact.

1. Reduction in the number of observation and hydrological stations

One of the key problems is the reduction in the number of observation stations and monitoring programmes. The methodological basis for forecasts relies on outdated methods and technologies, which negatively affects the quality of hydrological forecasts. These factors have led to a sustained deterioration in the quality of hydrological data.

In terms of coverage with hydrometeorological data, Kazakhstan's state network lags significantly behind developed countries. In the 1980s and 1990s, there were 1,983 hydrological stations operating in Kazakhstan, but by 2010 their number had decreased to 245. As of 2024, there are 377 hydrological stations operating in the country, compared with the minimum required number of 516. This indicator is planned to be achieved by 2050.

2. Low quality of observations

The condition of the network of routine observations of surface water pollution is also a matter of serious concern. There has been a reduction in the number of hydrochemical observation points, a decrease in the number of water and bottom sediment samples collected, as well as a reduction in the volume of analytical work performed. The absence of automated and remote methods for monitoring water regimes and quality, together with insufficient equipment with modern analytical laboratory instruments, determines the low quality of the observations conducted.

3. Limited availability of information and discrepancies between data from different sources

Another significant problem is the limited availability of information on the results of state monitoring of water bodies. There are discrepancies in water resource indicators provided by different sources, which results in the absence of objective and reliable information about the actual state of the country's water sector.

For example, according to data from the Water Resources Committee of the Ministry of Water Resources and Irrigation of the Republic of Kazakhstan, river flow amounted to 181 km³ in 2010 and almost 160 km³ in 2016. At the same time, the republican state enterprise "Kazhydromet" (hereinafter referred to as RSE "Kazhydromet") provides different data: 143.6 km³ in 2010 and slightly more than 146.0 km³ in 2016. Similar discrepancies are also observed in the number of rivers and temporary watercourses. Thus, according to the Water Resources Committee of the Ministry of Water Resources and Irrigation of the Republic of Kazakhstan, there are 39 thousand rivers and temporary watercourses, whereas according to RSE "Kazhydromet", their total number exceeds 84 thousand.

Under modern conditions, automation and digitalization are effective tools for improving the efficiency of management and technological processes. However, modern digital technologies with a unified digital database have not been introduced into Kazakhstan's water resources management system. Such technologies would make it possible to promptly consolidate up-to-date information, assess the situation, provide early warnings of emergencies and make accurate and timely decisions.

2.2.4. Deterioration of the environmental situation in view of climate change and anthropogenic pressure

1. Negative impact of climate change on water resources and hydrological cycles

According to forecasts by international organizations, there is a trend towards an increase in average temperatures in Central Asia and Kazakhstan. By 2030, temperatures may rise by +1.7–1.9°C, and by 2050 by up to +2–3°C.

According to RSE "Kazhydromet", a further increase in near-surface air temperatures of 0.8–1.2°C in all months of the year is expected in Kazakhstan, as well as a change in the average long-term annual precipitation by 1–3% by 2029.

The consequences of global climate change and rising temperatures are manifested in the increased frequency and scale of extreme weather events.

Climate change is primarily a water crisis. Changes in the basin hydrological cycles of Kazakhstan in response to global and regional warming will lead to increased moisture evaporation in river catchments, a decrease in water inflows into rivers, falling water levels in the Aral and Caspian Seas and Lake Balkhash, and increased demand for water resources for economic activities, including higher irrigation rates for agricultural crops.

According to UN data, glaciers in Central Asia have shrunk by 20–30% over the past 50 years due to climate change. At the same time, glaciers provide a significant volume of river flow during the growing season.

Changes in interannual and intra-annual variations in river flow – an increase in water inflows during the winter period and a decrease during the spring and summer periods – create additional restrictions on the use of water by economic sectors, particularly exacerbating the problem of timely water supply to agriculture.

The continuation of these trends in the future will inevitably lead to a sharp aggravation of water security problems and poses a real threat to the sustainable development of Central Asian countries.

In addition, there are currently no hydrological calculations regarding changes in the main hydrological characteristics of surface water flow associated with climatic factors. Nevertheless, these parameters are necessary for recalculating the capacity of spillway structures and ensuring guaranteed water releases from reservoirs.

2. Threat of floods, spring floods and droughts

Under normal climatic conditions, water bodies do not pose serious problems for the lives of the population and the country's economy. However, during extreme or extremely dry years, conditions for the formation of water flow may create a threat of emergencies, including the complete drying up of watercourses.

Flooding caused by spring or spring-summer high-water periods occurs in all regions of Kazakhstan. The probability of such situations arises on the rivers of southern Kazakhstan from February to July, on the mountain rivers of south-eastern and eastern Kazakhstan, as well as on the lowland rivers, from March to July.

For example, intensive spring floods in 2024, caused by widespread snowmelt, were observed in all catchment areas of water bodies in the Zhaiyk-Caspian, Tobol-Torgai, Ishim, Nura-Sarysu and Irtysh basins.

The abnormal floods were caused by the following factors:

Unfavourable climatic conditions. During the autumn period, soil layers became saturated with moisture, followed by freezing and the formation of an ice crust. During the winter period, significant snow accumulation was recorded, while in spring there was a sharp increase in temperature combined with heavy precipitation.

Natural changes in the profiles of riverbeds and tributaries, as well as their silting and overgrowth due to insufficient flow during periods of low water levels, which led to a reduction in maximum carrying capacity and increased flooding.

The location of civil infrastructure facilities in close proximity to rivers and their adjacent floodplain areas, which are susceptible to flooding, as a result of settlement planning that does not take potential flood risks into account.

An insufficiently developed system of flood protection structures (flood irrigation systems, protective embankments, drainage canals, small reservoirs, artificial basins, bank protection structures and other facilities) near settlements exposed to flooding risks. Such structures are in inadequate condition and are practically ownerless. Most of these structures were built in the 1960s and 1970s and have been operated for more than 50 years without major repairs or reconstruction.

The absence of specialized local organizations responsible for the operation of hydraulic structures in municipal ownership, as well as insufficient technical and staffing resources of the relevant enterprises.

Under such conditions, ensuring the proper functioning of hydraulic structures and responding adequately to potential flood threats may prove difficult, increasing the risk of emergencies and negative consequences for the population and infrastructure.

Until 1991, flood irrigation systems covering an area of up to 1 million hectares operated in the above-mentioned water management basins. In addition to retaining moisture in the soil to create a fodder base (hayfields), these systems played a significant role in retaining snow and preventing uncontrolled overflow of flood and meltwater. In 2024, during the flood period, approximately 1 billion m3 of meltwater was accumulated in flood irrigation systems in Akmola, West Kazakhstan, Aktobe and Pavlodar regions.

In accordance with the water legislation of the Republic of Kazakhstan, the construction of buildings and structures within the boundaries of water protection strips is prohibited. Nevertheless, more than 2 thousand houses, inhabited by approximately 10 thousand people, are located throughout the country within areas of potential risk.

In addition, the flood situation was caused by the absence or insufficient effectiveness of flood monitoring and forecasting, the lack of measurement automation, as well as the absence of mathematical modelling of flood inundation zones. These factors limit the ability to respond promptly to changes in water regimes and take the necessary measures to prevent emergencies. The country also lacks networks of hydrological stations on small water bodies, as well as a water accounting system in the catchment areas of these facilities.

In general, the risk management system in the field of water resources management, both during flood periods and during low-water periods, often demonstrates its inefficiency and deterioration.

Virtually every natural emergency has serious consequences. For example, floods and inundations can cause additional problems for the economy and the environment and worsen the sanitary and epidemiological situation. Areas subject to flooding, particularly prolonged flooding, are classified as high environmental risk zones associated with the potential spread of natural focal infections and epidemiological complications. Therefore, it is necessary to consider the possibility of strengthening control over drinking water supply sources.

Particular attention should be paid to the problem of drought, which has a significant impact on the country's food security, leading to reduced yields of agricultural crops and decreased food availability.

Kazakhstan, like other Central Asian countries, is highly susceptible to droughts.

In 2021, an emergency situation was declared in Mangystau, Kyzylorda and Turkistan regions as a result of drought. In 2023, in the Irtysh River basin, due to a decrease in lateral inflow to the Shulba Reservoir during the spring period and the threat of the Bukhtarma and Shulba reservoirs being drawn down to dead storage levels, the Irtysh River floodplain in Pavlodar Region was flooded only to an extent of 32.1%. As a result of the drought in 2023, 9.5 thousand hectares of sown areas perished in Zhambyl Region.

According to RSE "Kazhydromet", 9 of the 10 hottest years in Kazakhstan occurred after 2000.

At the same time, it should be noted that drought is neither directly mentioned nor defined in the regulatory legal documents of Kazakhstan.

In general, the development of unfavourable climatic and anthropogenic conditions creates a real threat of the emergence of new zones of environmental instability in a number of transboundary river basins of Kazakhstan, including Lake Balkhash, the Northern Aral Sea and the Zhaiyk River.

The transboundary endorheic basin of Lake Balkhash is a potential water crisis zone similar to the situation with the Aral Sea. During the conditionally natural period, the volume of renewable river flow resources in the Kazakh part of the basin amounted to 24.76 km3/year, of which the transboundary flow of the Ili River from the territory of China amounted to 11.45 km3/year, which ensured the average long-term lake level at an elevation of 341.0 m.

In general, there is a lack of comprehensive water resources management in the context of mitigating the consequences of drought.

The forecasting and analytical work of the emergency services of RSE "Kazhydromet" requires improvement, as the forecasting horizon is limited, which restricts the possibilities for promptly responding to emergencies. In most cases, response measures are taken after the event has occurred.

The cross-border water bodies pose a serious threat of floods and inundations, particularly during periods of seasonal high water and in the event of possible emergencies involving hydraulic structures or mountain lakes in neighboring countries. For example, the breach of the dam at the Sardoba Reservoir in 2020 had adverse consequences not only for Uzbekistan but also for 14 settlements in southern Kazakhstan, resulting in the evacuation of more than 30,000 people and causing significant damage to their property.

Water plays a central role in the development of the Central Asian region. The countries of Central Asia share common and limited water resources, which are vital for irrigated agriculture and energy supply. Hydropower accounts for approximately 90% of the region's energy needs.

According to the United Nations, 152 million hectares, or 38.4% of the land area in the Central Asian region, are affected by drought, of which 1.33% are subject to severe drought and 0.23% to extreme drought. This factor may lead to a decline in crop yields.

In this regard, cooperation and coordination of efforts with neighboring states in combating floods, inundations and drought are important areas of activity.

3. Low Quality of Water Resources

In areas of intensive economic activity, water bodies are polluted by consumer and industrial waste. As a result, the quality of surface water does not meet sanitary and hygienic standards.

The country's surface water bodies are intensively polluted by mining, metallurgical and chemical industry enterprises, agriculture and municipal services. Due to the lag in the availability of wastewater disposal systems, only 29% of wastewater from settlements in Kazakhstan undergoes secondary treatment before discharge (for comparison: in the United Kingdom – 94%, in Israel and Singapore – 100%).

To assess the environmental potential of a water body, Kazakhstan applies a unified classification of water quality in water bodies, which is divided into five classes, with a gradual transition from Class 1 waters of the "highest quality" to Class 5 waters of the "lowest quality".

Detailed information on the results of surface water quality monitoring is presented in Table 4.

Table 4. Surface Water Quality

Download

Water Quality Class¹Characteristics of Water by Type of Water UseWater Bodies and Water Quality Indicators for the First Half of 2023
Class 1 (highest quality)Water is suitable for all types of water use11 water bodies (9 rivers, 2 reservoirs): rivers: Esentai, Ulken Almaty, Kara Ertis, Arasan, Urzhar, Elek, Usolka, Ertis, Aksu; and reservoirs: Bukhtarma, Ust-Kamenogorsk
Class 2Water is suitable for fish breeding, recreation, irrigation and industry; simple water treatment methods are required for domestic and drinking water supply11 water bodies (10 rivers, 1 reservoir): rivers Shilik (total phosphorus), Korgas (total phosphorus), Turgen (total phosphorus, COD), Lepsi (total phosphorus), Aksu (total phosphorus, COD), Karatal (total phosphorus) in Almaty Region; Bukhtarma (manganese), Breksa (manganese), Ertis (manganese, suspended solids) in East Kazakhstan Region; Zhaiyk (suspended solids) in West Kazakhstan Region; reservoir Shortandy (nickel, COD) in Akmola Region
Class 3Water is suitable for recreation, irrigation and industry; water is suitable for breeding carp species; it is undesirable for salmon species; conventional and intensive water treatment methods are required for domestic and drinking water supply.24 water bodies (22 rivers, 2 reservoirs): rivers Ile (magnesium), Sharyn (magnesium), Tekes (magnesium), Bayankol (total phosphorus), Kaskelen (total phosphorus), Karkara (magnesium), Talgar (total phosphorus), Temerlik (magnesium, total phosphorus), Bettybulak (BOD5), Zhabay (magnesium, BOD5), Sekisovka (ammonium ion), Silety (magnesium, BOD5), Tikhaya (ammonium ion, cadmium), Ulba (cadmium), Glubochanka (magnesium), Krasnoyarka (magnesium, cadmium), Oba (suspended solids), Emel (magnesium), Assa (magnesium), Derkol (ammonium ion), Badam (magnesium, ammonium ion), Arys (ammonium ion); reservoirs Kapshagai (magnesium), Astana (total phosphorus, magnesium, BOD5)
> Class 3Water is suitable for irrigation and industry2 water bodies (2 rivers): Shu River (phenols) and Keles River (phenols)
Class 4Water is suitable for irrigation and industry; deep water treatment methods are required for domestic and drinking water supply.37 water bodies (31 rivers, 3 canals, 3 reservoirs): rivers Elek (ammonium ion, phenols², chromium (6+)²), Kargaly (ammonium ion, phenols²), Emba (ammonium ion, magnesium, phenols²), Temir (ammonium ion, phenols²), Or (ammonium ion, phenols²), Aktasty (ammonium ion, phenols²), Kosestek (ammonium ion, magnesium, phenols²), Oiyl (ammonium ion, phenols²), Ulken Kobda (ammonium ion, phenols²), Kara Kobda (ammonium ion, phenols²), Irgiz (ammonium ion, phenols²), Kishi Almaty (magnesium), Esik (suspended solids), Esil (magnesium, suspended solids, phenols²), Shagalaly (magnesium), Zhaiyk (magnesium), Peretaska tributary (magnesium), Yaik tributary (magnesium), Sharonov tributary (magnesium), Aksu (magnesium, sulfates), Karabalta (magnesium, sulfates), Toktash (magnesium, sulfates), Shyngyrlau (suspended solids), Saryozen (suspended solids), Karaozen (suspended solids), Ayet (magnesium, sulfates), Toguzak (magnesium), Uy (ammonium ion, magnesium), Zhelkuar (magnesium, mineralization, sulfates), Torgai (magnesium), Syr Darya (magnesium, phenols²), Nura-Esil Canal (magnesium), Koshim Canal (suspended solids), K. Satpayev Canal (magnesium); reservoirs Samarkand (magnesium), Sergeevskoye (suspended solids, phenols), Tasotkel (sulfates, magnesium)
Class 5 (lowest quality)Water is suitable only for certain types of industry – hydropower, mineral extraction and hydraulic transport2 water bodies (2 rivers): Makhovka River (phosphates), Sarykau River (sulfates)
> Class 5Water is unsuitable for all types of water use20 water bodies (15 rivers, 5 reservoirs): rivers Akbulak (COD, chlorides), Sarybulak (magnesium, mineralization, chlorides), Nura (total iron, manganese), Aksu (COD, chlorides), Kylshykty (magnesium, mineralization, chlorides), Kigash (suspended solids), Ayagoz (suspended solids), Kishi Karakozha (total iron, cadmium, manganese, copper, zinc), Talas (suspended solids), Tobyl (magnesium, mineralization, chlorides), Obagan (calcium, magnesium, mineralization, sulfates, chlorides, ammonium ion, suspended solids), Kara-Kengir (ammonium ion, calcium, magnesium, manganese, mineralization, chlorides), Sokyr (ammonium ion, total iron, manganese), Sherubainura (ammonium ion, total iron, manganese), Katta-Bugun (suspended solids); reservoirs Amankeldy (suspended solids), Karatomar (suspended solids), Zhogargy Tobyl (suspended solids), Kengir (manganese), Shardara (suspended solids)

Notes:

¹*Unified system for classifying water quality in water bodies (Order No. 151 of the Chairman of the Water Resources Committee of the Ministry of Agriculture of the Republic of Kazakhstan dated November 9, 2016);*

²*Substances are not subject to standardization for this class.*

Groundwater deposits used to supply cities are experiencing significant anthropogenic pressure and are susceptible to pollution due to the presence of pollution sources both within urban areas and in adjacent territories.

The main sources of groundwater pollution in the country are mining and processing enterprises, urban development facilities, livestock farms, agricultural lands, various settling ponds, storage facilities for solid and liquid waste, petroleum products, motor vehicles and others.

Large-scale groundwater pollution hotspots in Kazakhstan have developed within the territorial industrial complexes of Aktobe – Alga, Pavlodar – Ekibastuz, Karaganda – Temirtau, Zhambyl – Karatau, Shymkent, Eastern Kazakhstan and Semipalatinsk.

The existing level of anthropogenic pollution is one of the main causes of the degradation of rivers, reservoirs and lake systems, as well as the accumulation of pollutants in bottom sediments, aquatic vegetation and animal organisms. These substances, including toxic substances, deteriorate the quality of surface water in water bodies used as sources of drinking and domestic water supply, and also affect the habitats of aquatic biological resources.

2.2.5. Dependence on Transboundary Rivers

Due to geographical features, 7 out of 8 water management basins in Kazakhstan are largely dependent on the water management policies of neighboring countries.

In this regard, the most vulnerable are the Aral-Syr Darya (91%), Zhaiyk-Caspian (82%), Shu-Talas (74%) and Balkhash-Alakol (48%) water management basins, while the least vulnerable are the Tobyl-Torgai (12%) and Ertis (20%) water management basins.

According to the index of dependence on inflows from transboundary rivers originating in neighboring countries, Kazakhstan is in the same group as Israel and Portugal, which significantly increases the importance of regulating transboundary water flows in addressing the country's existing and potential water problems.

1. Water Relations Issues with Central Asian Countries

Water relations between the states of the Syr Darya River Basin are regulated by two main agreements:

1) Agreement between the Republic of Kazakhstan, the Kyrgyz Republic, the Republic of Tajikistan, Turkmenistan and the Republic of Uzbekistan on cooperation in the field of joint management of the use and protection of water resources of interstate sources dated February 18, 1992;

2) Agreement between the Government of the Republic of Kazakhstan and the Government of the Kyrgyz Republic on the Use of Water Management Facilities of Interstate Importance on the Shu and Talas Rivers dated January 21, 2000.

The need to develop dialogue with Central Asian countries is обусловed by significant changes in the region's water balance.

In recent years, the reduction in water flow in the Aral-Syr Darya water management basin has reached 38% (10.2 km³) on the Uzbek side, and in the Shu-Talas basin it has reached 32% (1.3 km³) on the Kyrgyz side.

2. Water Relations Issues with China

Today, water relations between Kazakhstan and China are regulated by the bilateral Intergovernmental Agreement on Cooperation in the Use and Protection of Transboundary Rivers dated September 12, 2001.

At the same time, this agreement is declarative in nature and does not provide for obligations regarding equal water allocation and joint management of transboundary rivers. Such bilateral agreements on water resource allocation exist only for the transboundary rivers Khorgos, Sumbe and Kaishybulak (Narynkol).

At the same time, the flow of the Ertis River has decreased by 21.5% (2.1 km³), while river inflow in the Balkhash-Alakol basin has decreased by 15.3% (2.3 km³) due to anthropogenic activities in China. Moreover, the further active development of Chinese territories against the backdrop of a growing population and expanding production capacities implies an increase in water withdrawals by China.

3. Water Relations Issues with Russia

Cooperation between Kazakhstan and Russia in the field of water resources is carried out on the basis of the bilateral Agreement on the Joint Use and Protection of Transboundary Water Bodies dated September 7, 2010. Most of the decisions adopted are being implemented.

However, in recent years, a 15% (1.3 km³) decrease in water inflows in the Zhaiyk-Caspian basin has been recorded.

2.2.6. Imperfections in Scientific and Methodological Support and Human Resources

1. Weak Research Base in the Field of Water Resources Management

Scientific and technical developments aimed at ensuring the development of hydro-reclamation and the water management complex cover a wide range of issues relating to strategic and operational water resources management, water management planning, the design of facilities and technologies, and the modelling and forecasting of the condition of water bodies. At the same time, insufficient attention is currently being paid to the development of science in the water management sector in Kazakhstan.

Ensuring scientifically sound solutions to these tasks requires strengthening the capacity of research organizations and creating conditions for attracting young researchers in order to maintain and develop existing scientific schools.

2. Insufficient Availability of Professional Personnel

There is a shortage of qualified personnel and young specialists at all levels of water resources management in Kazakhstan. Currently, only 200 specialists with higher education and 100 specialists with vocational and technical education graduate annually for the needs of the water management sector, and only 22% of them find employment.

Existing educational programmes do not provide a full range of knowledge, resulting in insufficient training of graduates. The level of preparedness of new specialists has declined significantly compared with the period before the 1990s.

The shortage of specialists in the territorial departments of basin inspectorates prevents the full exercise of state control over the use and protection of the water fund.

There is an acute shortage of specialists in the design and operation of hydraulic structures. The level of personnel training does not meet the requirements of scientific and design institutes.

Against the backdrop of the introduction of new technologies, the system of training and retraining personnel for the water sector is considered insufficiently effective.

There are 9 higher education institutions graduating specialists in water management, many of which lack appropriate teaching staff and laboratory facilities, which directly affects the quality of graduate training.

There are no specialized higher education institutions where specialized disciplines would be taught at an appropriate level and training programmes for specialists would be developed with maximum alignment with practical activities and the involvement of practitioners and researchers.

In most cases, training is provided in only one specialty – "Water Resources and Water Use", which is a broad-profile specialty and does not meet the qualification requirements for employees in the water sector under modern conditions. Personnel training is also carried out without proper coordination with water management organizations and enterprises.

In this regard, the training of engineering specialists in the following fields is relevant: "Hydro-reclamation", "Hydraulic Engineering Construction of River Structures and Hydroelectric Power Plants", "Mechanization of Hydro-reclamation Works", "Water Management Economics", "Hydrogeology and Engineering Geology", "Water Supply and Sewerage" and "Land Hydrology".

There is also a need to develop secondary vocational education for the training of mid-level personnel and skilled workers for water management organizations by improving educational programmes and establishing new colleges, taking into account the regional characteristics of water management infrastructure.

According to estimated forecasts, by 2029 the demand for highly qualified specialists will increase to 1,700 people, while their training will require up to 350 members of academic teaching staff, including 170 with academic degrees.

Due to low wages, difficulties in finding employment and the unwillingness of business entities to hire young specialists, most employees of water management organizations are people approaching retirement age. A dangerous trend has emerged in the disruption of generational continuity, since it takes at least 10–15 years to train and develop a highly qualified specialist.

2.2.7. Imperfections in the Institutional Environment and Legislative Framework

1. Inconsistency of State Policy on Water Resources Management

Currently, the functions of managing and protecting water resources and providing water to the population, the environment and economic sectors are distributed among various central government bodies.

The Ministry of Water Resources and Irrigation formulates and implements state policy in the field of the use and protection of the water fund, irrigation, drinking water supply outside settlements, and hydrological monitoring. In order to strengthen control over illegal water use, a new Committee for the Regulation, Protection and Use of Water Resources was established under the Ministry through the reorganization of the Water Management Committee.

The Ministry of Industry and Construction is responsible for drinking water supply and wastewater disposal within settlements, as well as geological exploration of subsoil resources.

The Ministry of Ecology and Natural Resources is responsible for intersectoral coordination in the field of environmental protection and meteorological and hydrological monitoring.

The Ministry of Agriculture is responsible for the agro-industrial complex, irrigated agriculture, agricultural land improvement, land resources, and the protection, reproduction and use of wildlife in the field of aquaculture.

The Ministry of Energy formulates and implements state policy in the field of hydropower.

The Ministry of Healthcare is responsible for sanitary and epidemiological monitoring of water and control over drinking water quality.

The Ministry of Emergency Situations coordinates issues related to the prevention and elimination of the consequences of emergencies associated with the harmful effects of water.

The Ministry of Digital Development, Innovation and Aerospace Industry provides satellite monitoring of the condition of water resources.

The Ministry of Science and Higher Education ensures the training of personnel for the water sector and the financing of scientific research in the water sector.

The Ministry of Foreign Affairs coordinates activities related to the interaction of the Ministry of Water Resources and Irrigation on transboundary rivers.

The Ministry of National Economy coordinates issues concerning tax payments for water resources, the implementation of investment projects in the water sector and the activities of the state-owned enterprise "Kazvodkhoz" operating under the right of economic management as a natural monopoly entity.

The fragmentation of functions makes it impossible to create an integrated organizational structure that combines domestic and foreign policy in the field of water resources protection and use, thereby hindering effective analysis, decision-making and preparedness for global climate and geopolitical challenges.

2. Issues of Water Legislation

The main legislative document governing the water sector – the Water Code of the Republic of Kazakhstan – was adopted in 2003. Numerous amendments and additions have resulted in a loss of consistency in law enforcement, deteriorating the condition of the water management sector. The current Water Code of the Republic of Kazakhstan is focused on the economic use of water resources without taking into account water conservation and the economical use of water. Significant technical and economic problems, as well as shortcomings in legal relations, regulatory control and strategic planning, remain.

The absence of clear legislative mechanisms for intersectoral cooperation makes it difficult to systematically plan and monitor measures to reduce water-related threats. The institutional structure and management system require development and increased efficiency. An important aspect is the integration of public organizations through basin councils and their active participation in the implementation of state policy.

Another problem in the water management sector is the existence of conflicts in water legislation concerning the adoption of a law on dam safety, the organization of comprehensive multi-factor surveys, and the determination and monitoring of safety criteria for hydraulic structures. As a result, inspections of the condition of hydraulic structures, including multi-factor surveys, are carried out inadequately. This prevents the reliable compilation of statistical information on the condition of the country's water management infrastructure. Furthermore, the accounting of water management infrastructure in Kazakhstan is not fully maintained.

Section 3. Review of International Experience

3.1. Experience of Countries in Improving the Efficiency of Water Resources Use

1. Experience of Israel

Israel is a world leader in the rational use of water resources. Through innovation, technology and effective management practices, the country has achieved significant success in this field.

Israel developed and implemented a drip irrigation system that makes it possible to save significant amounts of water. This technology delivers water directly to plant roots, reducing losses caused by evaporation and drainage. The use of sensors, drones and satellites is also provided for monitoring field conditions and accurately managing irrigation and fertilizer application.

Israel has the world's highest rate of wastewater reuse. Israel treats approximately 90% of its wastewater and reuses it mainly for agriculture.

In addition, Israel has built several large desalination plants on the Mediterranean coast, which provide a significant portion of its drinking water. Reverse osmosis technologies make it possible to produce clean water from seawater with minimal energy consumption.

Israel's tariff system encourages economical water use. Consumers pay for water according to a progressive tariff scale, which makes water use more rational.

Israel is also known for its strict standards and regulations governing the use and protection of water resources. Government authorities carefully monitor water use in various sectors of the economy.

2. Experience of Spain

Spain is divided into several water basins, each managed by a separate confederation. These confederations coordinate water resources management, including water allocation among regions and different users. Spain applies an integrated approach to watershed management, which includes taking into account the needs of agriculture, industry, the population and ecosystems, as well as monitoring water quality and protecting water resources.

In addition, Spain is actively modernizing its irrigation systems, moving from traditional methods to more efficient ones, such as drip irrigation and sprinkler systems (an irrigation method involving conditions similar to natural rainfall). At the same time, farmers receive economic incentives for implementing water-saving technologies, which helps reduce water consumption in agriculture, the main consumer of water resources.

Spain has built several desalination plants, particularly in regions experiencing freshwater shortages, such as the Canary Islands and the Mediterranean coast. These plants use reverse osmosis technologies to produce drinking water from seawater.

However, the cost of water desalination is high, so the government is actively seeking ways to reduce costs and improve the efficiency of these processes.

The Water Code of Spain is a document regulating the use and protection of water resources in the country. It establishes the rights and obligations of users, as well as measures to prevent pollution and degradation of water bodies. In addition to national legislation, regional laws and regulations adapted to the specific characteristics of local conditions and needs are in force.

Furthermore, Spain is actively researching climate change and its impact on water resources. Based on these data, adaptation strategies are being developed and measures to reduce the risk of floods and droughts are being implemented, such as the construction of reservoirs and canals.

3. Experience of Singapore

Singapore, which has limited natural water resources, has developed an innovative and efficient water resources management system known as the "Four National Taps". This system includes: rainwater collection through a network of reservoirs and canals, water imports from Malaysia under long-term agreements, seawater desalination using reverse osmosis technologies, and wastewater recycling through the NEWater programme, under which treated water is reused for industry and to replenish reservoirs.

Singapore actively invests in scientific research and development in the field of water technologies, as well as introducing advanced monitoring technologies, smart water supply management systems and public awareness programmes, ensuring sustainable and reliable water supply even under conditions of limited resources.

Singapore has created a reliable water supply system capable of adapting to future challenges: the construction of drainage systems and pumping stations to prevent flooding in urban areas.

4. Experience of the Netherlands

Multi-level water resources management in the Netherlands combines centralized strategic planning and financing at the national level with decentralized management through regional water boards (Waterschappen) and local authorities, ensuring adaptation to local conditions.

The system includes a complex network of dams, barriers and pumping stations to protect against floods, as well as programmes such as "Room for the River", which create additional channels and deepen riverbeds. The integration of nature-based solutions, such as floodplain restoration and the creation of wetlands, is combined with advanced engineering innovations.

Public participation and consultations play a key role, while awareness-raising and educational programmes strengthen public support for sustainable water resources management.

3.2. Experience of Countries in Promoting the Modernization and Development of Water Management Infrastructure

According to the International Commission on Large Dams, approximately 3,000 accidents at hydraulic facilities occur worldwide every year due to extremely high floods. These are associated with shortcomings in design and technical solutions for passing extreme flows, as well as improper operation by maintenance services. The most dangerous situations in terms of their consequences arise when hydraulic structures are subjected to water volumes exceeding their design capacity and when spillway structures are undersized.

As a result, during major floods, it is not possible to open the gates in a timely manner, and water overflows across the dam crest, leading to the destruction of structures.

International experience in the design, construction and operation of hydraulic structures shows that the risk of this threat can be eliminated or significantly reduced through an emergency prevention system. Addressing this problem requires clear organization of structural condition monitoring and prompt elimination of emergency situations. For this purpose, regular comprehensive inspections of hydraulic structures are carried out, with the development of information systems for assessing the condition and safety of hydraulic structures.

Particular attention is paid to the qualitative assessment, monitoring and control of the maintenance of water management facilities (dams and reservoirs) in order to prevent possible accidents and ensure safety.

1. Experience of Japan

In Japan, regular inspections of old dams are carried out by maintenance personnel. In addition to these, the Japan Dam Engineering Center conducts comprehensive inspections and assessments, mainly of multipurpose dams that are more than 20 or 30 years old, to evaluate structural safety, operational reliability and preparedness for emergency situations.

The safety of the dam body, gates and other facilities is assessed simultaneously with an examination of the relevant dam management methods:

Inspection and assessment based on management and observation activities.

Inspection and assessment based on modern design standards.

Inspection and assessment based on studies at the operating site.

Safety assessment and proposals for future management.

Analysis of the current flood control plan and operating rules is carried out together with an examination of the measures required for the effective use of existing dams:

Inspection and assessment of the flood control plan.

Inspection and control of operating rules.

Inspection based on past flood control experience.

Japan's experience demonstrates the use of high standards and technologies in dam safety, including modern regulations, equipment, diagnostic methods, supervisory activities and qualified personnel.

2. Experience of Germany

In Germany, hydraulic structures are equipped with all necessary instrumentation and control devices and are operated at a high professional level, with advanced technologies for monitoring and assessing reliable and safe operation.

A broad framework of regulatory legal and technical acts in the field of dam safety and other hydraulic structures has been established. Compliance with all requirements of these regulatory acts is ensured at every stage of the life cycle of hydraulic structures (design, construction, operation and reconstruction).

Through the automation of operations and the introduction of online monitoring, dams are operated reliably and safely. This also makes it possible to operate these facilities with a small number of personnel, averaging no more than five people.

Repair and construction works and dam modernization works are financed in the required amounts, ensuring their timely and high-quality implementation. All this makes it possible to ensure uninterrupted operation of dams and other hydraulic structures over the long term.

3.3. Experience of Countries in Information and Analytical Support and Monitoring of Water Resources Management Systems

3.3.1. Modern Observation and Monitoring Methods

1. Experience of Australia

Australia has implemented the Water Data Online system, which collects data from more than 4,000 observation stations. The data are available in real time and cover information on water flows, water quality and groundwater levels. This makes it possible to respond promptly to changes in water resources and make informed decisions.

2. Experience of the United States

The United States operates the National Water Information System (NWIS), which includes data from more than 18,000 observation stations across the country. Automation of data collection and the use of modern technologies, such as sensors and satellite observation, have significantly improved the quality and quantity of data, contributing to effective water resources management.

3. Experience of Israel

Israel uses modern technologies in water resources management, including sensors and remote sensing systems. The centralized water resources management system makes it possible to effectively monitor and distribute water resources, as well as promptly respond to emerging problems. Approximately 4,000 automated monitoring stations operate in the country, making it possible to track the condition of water bodies in real time and make informed decisions.

4. Experience of Japan

Japan actively uses automated water resources monitoring and management systems. Advanced information systems have been implemented in the country, making it possible to monitor the condition of water bodies in real time and forecast changes in their condition. More than 5,000 observation stations equipped with modern sensors and remote sensing technologies make it possible to respond promptly to changes in water resources and minimize the risks associated with floods and droughts.

3.3.2. Improving the Quality of Observations Through Modern Technologies

1. Experience of the European Union

Within the framework of the European Union Water Framework Directive (hereinafter referred to as the EU), a monitoring system has been developed that includes modern technologies for assessing water quality. The introduction of automated stations and the use of remote sensing make it possible to improve the quality and accuracy of observations. More than 100,000 water quality monitoring points operate in the EU, ensuring detailed and comprehensive monitoring of water resources.

2. Experience of the Netherlands

The Netherlands has established an integrated monitoring system that uses automatic sensors to collect water quality data. The system includes more than 1,200 automated stations providing real-time data. This makes it possible to respond promptly to changes and make informed water resources management decisions. The data are available to the public through online platforms, increasing transparency.

3.3.3. Centralized Data Systems to Improve Accessibility and Consistency

1. Experience of Canada

Canada has implemented an information exchange system between various levels of government and agencies, which makes it possible to centrally store and process data on water resources. The National Water Monitoring Program combines data from more than 2,000 observation stations. This reduces the risks of data inconsistencies and increases data accessibility for all stakeholders, including the government, scientific institutions and public organizations.

2. Experience of Germany

Germany has developed the National Water Resources Database (WaBiDa), which combines data from more than 15,000 observation stations and makes them available for analysis and decision-making. The centralized portal simplifies access to and analysis of information for various stakeholders, minimizing discrepancies in data and ensuring their reliability.

3.4. Experience of Countries in Improving the Environmental Situation and Adapting to Climate Change

3.4.1. Impact of Climate on Water Resources Management

1. European Water Regulators

Adaptation is aimed at making adjustments to existing systems and methods in order to minimize the adverse consequences of climate change. This may include introducing water-saving technologies, redesigning infrastructure to withstand extreme weather events, or changing water allocation policies to account for changing precipitation patterns.

Mitigation measures in the context of water resources management may include switching to energy-efficient water treatment facilities, promoting sustainable agriculture that requires less water, or protecting and restoring natural water systems. While adaptation addresses the symptoms of climate change, mitigation measures address its root causes, and both are necessary for a comprehensive approach to sustainable water resources management.

2. United Nations Organizations

Rainwater harvesting – capturing rainwater is particularly useful in regions with uneven precipitation distribution in order to increase resilience to shocks and ensure water reserves during dry periods. Methods include rooftop harvesting for small-scale use and earth dams to slow runoff, reduce soil erosion and increase aquifer recharge.

Implementation of climate-smart agriculture – using conservation methods to improve organic matter content and increase moisture retention in soil; drip irrigation; reducing post-harvest losses and food waste; and converting waste into a source of nutrients or biofuel/biogas.

Wastewater reuse – unconventional water resources, such as properly treated wastewater, can be used for irrigation, as well as for industrial and municipal purposes. Safe wastewater management is an affordable and sustainable source of water.

Groundwater use – in many places, groundwater is overused and polluted; in other places, its availability is unknown. Research, protection and sustainable use of groundwater are crucial for adapting to climate change and meeting the needs of a growing population.

Various studies involving United Nations organizations and agencies identify the following water-related climate change adaptation challenges:

Risks and uncertainty – risks and uncertainty can be reduced by applying approaches and technological advances that help understand and quantify the expected impact of climate change on the water resources of a given river basin, community, location or ecosystem.

Too little water – growing competing demand and excessive abstraction of groundwater and surface water, as well as uncoordinated resource development for different purposes simultaneously, are common causes of water scarcity in many regions.

Too much water – rising temperatures mean that the atmosphere can hold increasing amounts of moisture, leading to an increase in potential precipitation volumes and, consequently, a higher risk of floods. Countries will have to adapt to river floods, flash floods, urban floods and sewer system overflows, as well as flood risks resulting from glacial lake outbursts, which is particularly relevant in the context of global warming.

Water pollution – climate change affects the global hydrological cycle as a whole, and rising temperatures may have a direct connection with water quality. Factors contributing to deteriorating water quality include increased frequency of floods and droughts, as well as rising water temperatures – all of which, combined with the impact of human activities, remain major causes of water quality deterioration (for example, industrial accidents). The lack of proper wastewater treatment, growing pressure from population growth and limited capacity of treatment systems are issues that must be addressed alongside efforts to mitigate the effects of climate change. Nutrient pollution (particularly phosphorus and nitrates) resulting from agricultural activities and domestic wastewater is a current water resources management problem and one of the main threats to water quality and the health of freshwater ecosystems. As a result of climate change, more intense precipitation may contribute to increased nutrient runoff and, consequently, eutrophication of water bodies. The eutrophication process is also intensified at higher temperatures, which support algae proliferation, leading to oxygen depletion in surface waters and the formation of dead zones.

Disaster preparedness – today, hydrological disasters account for the largest share of natural disasters worldwide, causing thousands of deaths and annual economic damage. Climate change is expected to exacerbate these losses due to the increased frequency of floods and droughts, as well as risks associated with glacial lake outbursts. A wide range of climate change adaptation measures aimed at mitigating the consequences of floods, droughts and natural disasters has already been mentioned. In many cases, these adaptation measures can only limit the scale and mitigate the severity of the consequences of natural disasters, but cannot prevent them completely. In addition, appropriate disaster preparedness measures must be taken to ensure the evacuation of people and the protection of critical infrastructure.

3.4.2. Prevention of Floods, Flash Floods and Droughts

Flood disasters account for approximately one-third of all natural disasters worldwide (in terms of both number and economic losses) and cause more than half of all casualties.

A review of international experience shows that countries pay increased attention to measures that can significantly reduce the risk of flood-related consequences and limit material damage and human casualties.

1. Examples of Permanent Flood Protection Measures

Rain gardens – urban spaces are transformed into green, absorbent, multifunctional areas where perennial wetland plants of local species are planted. These plants absorb water during precipitation and subsequently release water vapor back into the atmosphere.

Underground reservoirs – storage facilities for the temporary accumulation of meltwater and its subsequent controlled discharge into the hydraulic system. As water accumulates in huge underground reservoirs, it does not continue moving and does not form large stormwater flows that would later be impossible to control.

Floodable spaces – specially designated plots and territories intended for the temporary storage of excess water during floods, or additional channels for water during river overflows.

Inflatable dams – these are sleeves sealed at both ends, laid across a canal or riverbed on a concrete foundation and attached to it. In winter, their casing is filled with air to prevent damage caused by freezing water, and before the spring high-water season, it is filled with water so that the hydraulic structure can withstand heavy loads.

2. Examples of Temporary Flood Protection Measures

Absorbent bags consisting of a water-reactive element made of nonwoven outer material with a superabsorbent core. Before use, they weigh less than 0.5 kg, but once they come into contact with water, they can absorb up to approximately 20 liters.

Modular protective barriers made of low-density polyethylene, which allows the product to be both rigid and flexible. One block weighs only 40 kg. This makes the installation process quick and easy. Once the blocks have been installed, they must be filled with water through openings located at the top of each block. A pump can fill the wall with water to an impressive weight of 630 kg within a few seconds.

Prefabricated metal protective fences consist of horizontal metal crossbars with rubber seals between them, which are inserted into steel supports secured with bolts to a concrete barrier. These crossbars, made of hollow aluminum profiles, fill with water themselves, press against one another and thus ensure watertightness.

Mobile water-filled dams are reusable structures made of durable composite material consisting of multiple layers and filled with water.

3. Examples of Flood Forecasting Elements Worldwide

Information and analytical support and monitoring are key elements of an effective water resources management system. The main aspects of this topic are as follows:

Data collection and monitoring – deployment of sensor networks and IoT devices to collect real-time water quality data (the United States, Canada, China).

Use of big data analysis and machine learning methods to process huge volumes of data received from sensors.

Involvement of citizens in water quality monitoring through citizen science programmes and data-sharing platforms (the United Kingdom).

Data storage and management (general practice in many countries). Creation of integrated information systems for storing and managing water resources data.

Ensuring access to data through web portals and user interfaces.

Data analysis and visualization – application of data visualization methods, such as interactive dashboards and geospatial mapping, to identify spatial and temporal patterns.

Use of data to develop water resources policies and new projects.

Decision-making support. Data analysis to identify trends, anomalies and interrelationships that may be overlooked through traditional analysis.

Use of data to inform decision-making processes in water resources management, such as the development of basin management plans, assessment of applications for water use licenses, etc.

Hydrological modelling is used to assess the impact of floods. Integration of hydrological knowledge based on machine learning can improve snowmelt modelling capabilities (for example, Support Vector Machine, Multilayer Perceptron and Wavelet Neural Network methods), which are actively used and studied in the United States, Canada, Australia, China and European countries. Detailed consideration of the effects of snowstorms (snow drifting), soil freezing and thawing, as well as rain-on-snow events, will expand the capabilities of modelling snowmelt runoff in hydrological models.

Artificial neural networks (artificial neural network) show promising results in flood control by forecasting river flow and are actively being developed and studied in the United States, Canada, Australia, China and European countries.

A digital twin visualizes, analyzes and provides automated decision-making support, generates detailed reports on the structural integrity and reliability of hydraulic structures, and is used in the United Kingdom, Portugal, Germany and China.

Internet of Things (IoT) and virtual reality (VR) – IoT improves the management of information systems, particularly in the case of machine-to-machine interaction. Artificial intelligence can help derive benefits from weather forecasts and climate change science, while VR contributes to improved data visualization; its application is being studied in the United States, Israel and European countries.

Google Research uses artificial intelligence to accurately forecast river floods based on news reports in more than 80 countries up to 7 days before their occurrence, including in vulnerable regions with data shortages.

4. Examples of Flood Monitoring Elements Worldwide

Earth remote sensing provides real-time data.

Radars and sensors – synthetic-aperture radar is used to create a two-dimensional or three-dimensional reconstruction of an object. An edge detection sensor is used to detect edges and determine the horizontal waterline or dam height through detectors.

Unmanned aerial vehicles (hereinafter referred to as UAVs) – drones used for rapid data collection and to assist in disaster management tasks. Images from UAVs obtained through photogrammetry using a satellite navigation system make it possible to obtain accurate and high-quality spatial data.

Bathymetric surveys – data obtained using special technical equipment (echo sounders) can be used for analysis.

Forecasting and monitoring, as well as permanent and temporary flood protection measures, are activities within flood control policy, which encompasses a comprehensive systematic process of interrelated stages and represents a complementary ecosystem. For example, the flood control policy of European countries consists of the following:

Flood risk prevention ("keeping people away from water") – proactive spatial policy that includes the construction of houses and settlements outside flood-prone areas.

Flood protection ("keeping water away from people") – construction of hydraulic structures and river cleaning, dredging and bank reinforcement activities.

Flood impact mitigation ("reducing consequences within vulnerable areas") – flood containment and construction of temporary protective barriers, as well as the use of urban green infrastructure (for example, controlled flooding of parks).

Flood preparedness – systematic conducting of exercises, establishment of a warning system, operational weather forecasting and communicating evacuation plans to the population. It is important to ensure that warnings reach people effectively ("pushing") and to evacuate people in advance ("pulling").

Flood recovery – a plan of measures for the reconstruction and restoration of territories, payment of compensation to victims and provision of loans to local businesses.

According to international experience, the main focus in combating floods and flash floods is on providing the population with complete and timely information and modelling the development of emergency situations.

5. Experience of the Netherlands

The following principles are used to combat floods:

1) providing the population with complete and timely information;

2) forecasting emergency situations instead of reacting to them;

3) continuous water resources management and maintaining the relevant water management infrastructure in proper condition (construction of dams and embankments and their modernization);

4) territorial planning prohibiting construction in river floodplains;

5) responsibility for ensuring safety lies with everyone – the government, local authorities, water management administrations and citizens themselves. For example, in the event of natural emergencies, despite the stable operation of the water supply system, responsibilities for combating them are also assigned to owners of buildings and other facilities.

6. Experience of the EU

The European Flood Awareness System (hereinafter referred to as EFAS) operates in Europe. EFAS can provide medium-range flood modelling throughout the EU with a lead time (usually three to four days or more).

Twice a day, the EFAS system receives approximately 70 different digital weather forecasts from the meteorological services of European countries, as well as weather and river flow observation results conducted by several European organizations in near-real time. The data are fed into the hydrological modelling system (LISFLOOD), which generates 70 forecasts of river flow conditions.

Statistical comparisons with past floods enable EFAS to determine the potential for critical warning threshold values to be exceeded within the forecast period.

In this case, electronic messages containing flood warnings and information on the probability of flooding are sent to the relevant national hydrological services. These services can verify the results on site and access all alerts through a secure web server.

7. Experience of the United States

In the United States, the Flash Flood Guidance (FFG) technology, developed by specialists from the US National Weather Service and the Hydrologic Research Center in San Diego, is used for flood forecasting and operational warning. FFG technology is designed to identify in real time areas where rapidly developing flash floods are expected to form, including in small river basins not equipped with hydrological observation systems. A distinctive feature of this system is its advanced precipitation field assessment module based on radar data (NEXRAD systems), adjusted using the ground-based precipitation gauge network. The precipitation fields obtained using this technology are used as input data for the snowpack formation and melting model and the soil moisture calculation model. The system provides fully automated data collection and processing for modelling and issuing forecast information.

The technology generates output fields of indicators reflecting the possibility of flood formation, an indicator of the threat of dangerous flood formation, as well as an assessment of forecast uncertainty. The technology has a well-developed interface and allows output products to be presented in text formats, as well as in the form of maps and graphs.

8. Experience of Austria

An advanced operational flood forecasting system has also been established in Austria. It provides forecasts with a time resolution of 15 minutes and a lead time of up to 48 hours. The input meteorological data consist of weighted average precipitation forecast fields from the ALADIN and ECMWF models. The parameters of the hydrological model are distributed across elements of a regular grid with an area of 1 km². For each cell, calculations are made of snowpack dynamics, soil moisture movement processes and runoff transformation. The linear reservoir method is used to calculate hillslope routing, while a lumped-parameter model is used to calculate channel routing.

The system makes it possible to forecast floods associated with both intense precipitation and snowmelt in mountainous areas. The runoff forecast error of this model is 10–30% with a lead time of up to 24 hours.

9. Experience of Japan

In combating natural disasters, Japan focuses primarily on comprehensive public preparedness for natural disasters and actions to be taken after they occur. A system of regularly conducted exercises operates effectively and covers virtually all segments of the population.

10. Experience of China

China is one of the countries particularly severely affected by floods. Under the influence of the monsoon climate, precipitation in China is unevenly distributed; during the period from June to September, it can account for more than 70% of annual precipitation and decreases from southeast to northwest. The country's unique geographical and climatic conditions lead to severe droughts and floods. Since 1949, more than 50 major floods and 17 severe droughts have occurred, meaning that, on average, one natural disaster occurs every year.

In this regard, the Chinese government is taking effective measures to strengthen not only flood control but also drought management, which include: improving the organizational system and legislation; implementing a system of responsibility; enhancing advance planning; improving natural disaster forecasting; strengthening engineering support and water transfer arrangements; improving human resources support; and strengthening operational disaster response management.

As part of improving the organizational system, a command system for combating droughts and floods has been established at the national level (the Central Headquarters for Flood Control, established under the State Council of China on June 7, 1950, which was transformed in 1993 into the State Headquarters for Flood and Drought Control under the State Council of China (hereinafter referred to as the Headquarters)), as well as at the river basin and regional levels. The Head of the Headquarters is the Vice Premier of the State Council of China, the Deputy Head is the Minister of Water Resources of China, and its members are the heads of government departments. China has also adopted laws on flood control and regulations on flood and drought management. Headquarters at all levels have contingency plans for combating floods and droughts and periodically improve them.

A particularly important role is played by the modern monitoring and forecasting system for water bodies, precipitation and typhoon development established in China, which operates more than 70,000 observation stations. Automatic hydrological forecasting systems and flood diversion systems have been established at major and important medium-sized reservoirs. In the event of floods, headquarters at all levels must assess the performance of hydraulic structures and regulate floodwaters through interception, diversion, storage and discharge. During severe droughts, water resources are transferred on the basis of scientific research.

Thanks to this work and broad public participation, the Chinese government has achieved certain successes. It has been calculated that, since 1949, economic losses avoided by the country have amounted to 4.24 trillion yuan, while the number of deaths had decreased 6.5 times by 2001. Despite the achievements, the government continues working to improve the regulatory system.

Work is underway to establish a national flood and drought prevention system, increase the accuracy of monitoring and forecasts, and improve the "Joint Measurement, Joint Prevention" system.

Overall, it should be noted that drought prevention and drought risk mitigation require significantly lower costs than response and emergency measures.

3.4.3. Protection of Water Resources from Pollution

1. Experience of the EU

The experience of EU Member States has made it possible to achieve significant results in water quality management. In particular, a number of EU directives, such as the Water Framework Directive, the Drinking Water Directive, the Urban Wastewater Treatment Directive, the Bathing Water Directive and several other related directives, establish mandatory quality targets for drinking water and the protection of public health from the adverse effects of any pollution of water intended for human consumption. The same indicators have been established to protect the environment from the adverse effects of discharges of urban and industrial wastewater.

Germany has achieved the greatest success among EU countries in protecting water bodies from pollution. Thanks to the construction of more than 10,000 biological treatment plants in the municipal sector and intensive wastewater treatment at industrial enterprises, the discharge of pollutants into water bodies has been significantly reduced.

3.5. Experience of Countries in the Field of Transboundary Cooperation

1. Experience of North American Countries

In the 1990s, it was observed that the rapid development of cities and industry was causing serious environmental damage in areas adjacent to the Great Lakes. Studies showed that huge quantities of toxic pollutants were entering the lakes from various sources, such as wastewater and acid rain. The problem of acid rain was particularly acute, since a significant proportion of it, up to 50%, was generated in the United States and transported to Canada.

To address the problem, in the first half of the 1990s, the United States and Canada developed the Great Lakes Toxic Substances Control Strategy, which began to be implemented in 1997. The strategy includes measures related to replacing highly toxic chemicals in industrial processes with low-toxicity alternatives and gradually phasing out substances that pose risks to human health and the environment.

2. Experience of South American Countries

During the water crisis of 2020–2021, three countries (Argentina, Brazil and Paraguay) in the basin of the transboundary Paraná River faced three different challenges: the need to generate hydroelectric power, the need to maintain river navigation and the need for water from the Paraná River.

To address this problem, a special intergovernmental meeting was established with the participation of the governments of three countries – Brazil and Paraguay, which operate the Itaipu Dam, and Argentina, which has a separate agreement because it is located downstream along the Paraná River. Other key stakeholders dependent on the river, including businesses and local communities, were also involved in the meeting.

As a result, a technical report was prepared, which made it possible to calculate and measure the needs of each sector. Consequently, so-called "water windows for special operations" were created, meaning that the dam opened its gates based on this assessment of needs. During the water crisis, this method, based on the provisions of the UN Convention on "equitable and reasonable utilization", enabled the countries of the Paraná River Basin to manage potential tensions among river users.

3. Experience of the EU

In Europe, transboundary water cooperation is one of the key priorities due to the presence of numerous shared river basins on the continent.

The EU has played an important role in developing cooperation between Member States through directives such as the Water Framework Directive and the Floods Directive, which are aimed at improving water quality, combating floods and strengthening transboundary cooperation.

The Danube River, which flows through 19 European countries, is an example of successful transboundary water cooperation. The International Commission for the Protection of the Danube River (ICPDR) brings together riparian states to coordinate efforts in water resources management, pollution control and biodiversity conservation in the Danube River Basin.

Another example is the Rhine River, where countries such as Germany, France, Switzerland and the Netherlands have established the International Commission for the Protection of the Rhine (ICPR) to address issues relating to water quality, flood management and sustainable navigation along the river.

3.6. Experience of Countries in Improving Scientific and Methodological Support and Human Resources

3.6.1. Improvement of Scientific and Methodological Support

1. Experience of Israel

Israel is a world leader in water resources management, particularly under conditions of water scarcity. Advanced technologies for water desalination, wastewater reuse and drip irrigation systems have been developed and implemented here, making it possible to use every liter of water efficiently. Israeli scientists actively cooperate with international colleagues, developing joint projects and sharing their achievements.

2. Experience of the United States

The United States also pays considerable attention to water management issues. Technologies for monitoring and managing water resources using satellite data and information systems are widely applied here. Programmes for the restoration and protection of aquatic ecosystems, as well as scientific research aimed at improving drinking water quality and optimizing water consumption in agriculture and industry, play an important role.

3. Experience of Canada

Canada is renowned for its advanced research in water resources management, particularly in the context of large watersheds and lakes. Methods for assessing and forecasting water resources, as well as strategies for adapting to climate change, are actively being developed here. Canadian scientists are working on the development of comprehensive models of water systems that help decision-making at various levels of management.

4. Experience of the EU

In Europe, scientific research and development in the field of water management are supported at both EU and national government levels. Particular attention is paid to projects on integrated water resources management, improving wastewater treatment methods and creating sustainable water supply systems. European countries are actively introducing innovative technologies and developing new approaches to water resources management under changing climate conditions.

The experience of these countries shows that successfully addressing challenges in the water management sector requires a comprehensive approach combining scientific research, innovative technologies and effective management. Kazakhstan should take this international experience into account and actively develop its own scientific schools and infrastructure to improve the efficiency of water resources management.

3.6.2. Improvement of Human Resources

1. Experience of the United States

The United States has an extensive system for training and retraining specialists in the water management sector. Leading universities, such as the University of California, Berkeley and the University of Texas at Austin, offer specialized programmes that include courses in hydraulic engineering, water resources management and environmental engineering. In addition, government and private organizations actively participate in professional development through seminars, advanced training courses and internships. Federal programmes, such as the National Water Training Center, provide resources for training and retraining specialists.

2. Experience of Israel

Israel actively invests in education and scientific research. The Technion – Israel Institute of Technology offers advanced programmes in water technologies and resource management. In addition, Israel has an extensive system of professional development and internships for water management specialists, including cooperation with international organizations and participation in global scientific projects.

3. Experience of the EU

In Europe, education and professional training in the field of water management are coordinated at both national and pan-European levels. Programmes such as Erasmus+ and Horizon 2020 promote knowledge exchange and professional development through international cooperation and research projects. Leading European universities, such as Delft University of Technology (the Netherlands) and the Technical University of Munich (Germany), offer specialized courses and programmes in water resources management and hydraulic engineering.

4. Experience of Canada

Canada has a well-developed system for training personnel for the water management sector. The University of British Columbia and the University of Toronto offer programmes focused on water resources management, hydraulic engineering and environmental engineering. Canada also actively supports professional development through federal and provincial programmes aimed at improving specialists' qualifications, including training and certification in new technologies and water resources management methods.

5. Experience of Central Asian Countries

In Uzbekistan, bachelor's degree students are trained in 17 specialties and master's degree students in 14. At the Tashkent Institute of Irrigation and Agricultural Mechanization Engineers, an average of 9,500 hours is allocated for the entire period of bachelor's degree programmes.

In Kyrgyzstan and Uzbekistan, curricula are distinguished by their balance and rational structure. Humanities disciplines account for 15–17% of the total workload, while general professional disciplines account for 38.3% and 43.7%, respectively.

Great importance is attached to students completing practical training. In Uzbekistan, 2,160 hours are allocated for these purposes, while in Kyrgyzstan the figure is 750 hours.

In Tajikistan, 38.3% of the total number of study hours is allocated to courses in the water sector, ensuring flexibility in the choice of specialized educational fields and orienting teaching staff towards the needs of production.

Furthermore, in international practice, countries around the world continuously work to improve the effectiveness of educational programmes and the professional development of specialists in the water sector. For example, establishing a National Advanced Training Center for the Water Sector through close cooperation with international educational and research organizations could help address the shortage of qualified personnel. This would make it possible to adopt advanced technologies, as well as methods of training specialists and water resources management in general, adapting them to the conditions of Kazakhstan.

Countries around the world are also actively developing internship and exchange programmes for students and young specialists, enabling them to gain practical experience at leading global water management centers. Introducing dual-degree programmes with leading international universities in the field of water resources could improve the training of Kazakhstani specialists and increase their competitiveness in the global labor market.

The introduction of dual-degree programmes with leading international universities in the field of water resources, as well as new technologies and teaching methods (for example, online courses and webinars), particularly for remote regions, could contribute to improving the level of professional training of domestic specialists.

3.7. Experience of Countries in Improving the Institutional Environment and Legislative Framework

3.7.1. Integrated Approach to Water Resources Management

In the modern world, water resources management is carried out at various levels: interstate, national, basin, territorial, as well as at the level of water users. Progressive international experience demonstrates that the best practice in water resources management is the use of an integrated approach, which includes six main components:

- basin-based management;

- integrated management of water and land resources;

- joint consideration of social, economic and environmental factors;

- inclusion of surface and groundwater resources in planning;

- public participation in the planning process;

- transparency and accountability in the decision-making process.

3.7.2. Water Legislation

The water legislation of most countries of the world provides for state regulation in the field of water resources use and protection, with the establishment of state water management authorities. In economically developed countries, legislation establishes the need to develop long-term programmes for the integrated use and protection of water bodies in order to reduce their pollution levels and prevent the depletion of water resources.

1. EU Experience

Since 2000, the EU Water Framework Directive has been in force and is binding on all EU Member States. The main principles of the Directive include:

Ensuring the protection, improvement and restoration of all surface water bodies.

Management of water resources within the boundaries of a river basin, with the establishment of a special state management body;

Development of a long-term action programme for each river basin, to be reviewed and updated every 6 years, with mandatory publication for broad public discussion;

Active involvement of all stakeholders in the development, adjustment and implementation of basin programmes;

The principle of full cost recovery for the study, protection and reproduction of water resources, and the restoration of water bodies through revenues from water use and pollution charges;

Licensing of water use based on permissible impact standards and target water quality indicators;

Monitoring the condition of water bodies and specially protected natural areas;

Coordination of actions concerning transboundary watercourses with neighbouring countries and the establishment of an interstate management body.

2. Experience of Germany

Germany is one of the most advanced countries in the field of water resources management, extending its efforts not only to the protection of water bodies but also to the economical consumption of drinking water and the reduction of water consumption in industry. The central federal law is the Law "On the Organisation of Water Management" (1957), which states that "water is an integral part of nature and is protected as a habitat for animals and plants". The principle of water use is that "everything that is not expressly permitted is prohibited". Water use is subject to obtaining permits, the issuance of which is guided by environmental standards.

The second important law is the Law "On Charges for the Discharge of Wastewater into Water Bodies". The basis for calculating the charge is the "pollution units" established for the quantity of pollutants in wastewater. Revenue from these charges is transferred to the budgets of the federal states and spent on water conservation measures.

In Germany, state responsibilities in the field of water resources are addressed by the Federal Government, the 16 federal states and municipalities. Local authorities have their own water laws, which do not contradict federal legislation. At the river basin level, the federal states have working groups, while the Federal Government is involved in resolving issues related to international river basins.

3. Experience of France

French legislation is considered one of the most advanced in the world, according to which water is state property. The current water legislation is most closely aligned with the EU Water Framework Directive. The Water Law (1964) introduced changes to the system of state water resources management: the country's territory was divided into 6 basins, and basin committees and agencies were established.

In 1992, amendments were introduced to the Water Law: the concept of joint management of surface and groundwater was defined, and basin committees were tasked with developing master plans for the development and management of the basin's water management system, as well as development plans for sub-basins (tributary basins). Basin committees determine the basin development policy and establish charges for water use. The Committee develops a Framework Programme for the planning and management of the basin's water resources, which is divided into sections accountable to local water commissions. Each commission develops its own water resources planning and management programme.

Basin agencies are executive state financial and technical bodies that implement basin policies on the basis of self-financing, using economic incentives (charges and subsidies).

4. Experience of Spain

In 2000, the EU adopted the Water Framework Directive as a unified framework mechanism. In this regard, in 2003, Spain revised its Law "On Water Resources" (1985), incorporating the main provisions of the Directive. In 2009, planning for water management activities in catchment basins began, with an emphasis on public participation and the environmental condition of water resources. The country established a comprehensive monitoring programme to assess the condition of water bodies and identify sources of pollution. The regulation of water resources is based on multi-component legal acts, instruments and policy mechanisms.

Joint efforts by public authorities and private businesses ensure the success of the model. Overall water resources management is in the hands of the state, but almost half of the population is served by private or mixed public-private companies. The financing of large-scale infrastructure projects and inter-basin water transfer schemes is carried out by the state.

5. Experience of the USA

The basis of water legislation in the USA is the legislation of individual states. There is no single federal authority responsible for basin planning and management. Responsibilities and powers in water management are distributed among numerous federal, state and local authorities, non-governmental organisations and private companies. In the USA, surface and groundwater are regulated by different legal provisions, with the main emphasis placed on the system of water use permits.

6. Experience of Australia

The impetus for reforms in Australia's water sector was the drought of 1994. A National Water Plan was developed with the participation of scientists and agreed upon by the Government and the states. Later, the National Water Commission was established. The state bears primary responsibility for water resources management, setting objectives and developing the capacity to achieve them.

Section 4. Vision for the Development of the Water Sector

The development of the water sector will be carried out taking into account the need for Kazakhstan to fulfil its commitments to achieving the Sustainable Development Goals in the area of ensuring the availability and sustainable use of water resources.

The main vectors for the development of the water sector in the Republic of Kazakhstan are the creation of conditions to meet the growing water needs of the population, the environment and economic sectors, and ensuring effective water resources management in the context of global climate change.

Through the rational use of available water resources, including the active introduction of water-saving irrigation technologies, the prerequisites will be created for the transition from "resource management" to "demand management", the main principle of which is to use less water to meet the same needs.

The introduction of water-saving irrigation technologies will make it possible to save 20–30% of irrigation water, which will enable additional areas to be brought under irrigation, as well as increase the productivity of water resource use by a factor of 2.0–2.5.

Increasing the volume of treated wastewater used will reduce the anthropogenic pressure on water bodies.

As a result of the implementation of the Concept, by 2030, unproductive water losses during transportation will be reduced, a system of hydrogeological and land reclamation monitoring will be developed to improve the condition of irrigated lands, and the technical condition of hydraulic structures will be improved to ensure a guaranteed water supply to economic sectors and reduce the risk of emergencies.

The introduction of digital technologies and intelligent systems in the field of water resources management will make it possible to automate the centralised collection, storage and analysis of data, thereby ensuring a more effective management and control system.

To ensure the effective functioning of the water sector, measures will be implemented to provide scientific, human and resource support, strengthen the institutional environment and improve the regulatory legal framework in the field of water relations.

Improving the effectiveness and coordination of the activities of government bodies in achieving priority goals and objectives in the field of water relations will contribute to the further development of the sector.

The country's dependence on transboundary flows will be reduced through the joint resolution of issues concerning the use of transboundary water bodies and the improvement of interstate water relations.

Legislative regulation aimed at preserving the country's water resource potential will establish sustainable foundations for management and requirements concerning the protection and use of the water fund, water conservation, the economic regulatory mechanism, interstate cooperation on transboundary watercourses, and the prevention of harmful impacts as the basis of water security.

Section 5. Basic Principles and Approaches to the Development of the Water Sector

For the purpose of effectively addressing the assigned tasks, the main principles are:

1) the principle of human-centredness – when making any decision, the person and their interests come first (in the context of this Concept, this means achieving and maintaining an environmentally safe and economically optimal level of water use and protection of the water fund, water supply and wastewater disposal in order to preserve and improve the living conditions of the population and the environment);

2) the principle of transparency (openness) – mandatory publication of information on the implementation of the Concept for the Development of the Water Resources Management System of the Republic of Kazakhstan, with the exception of information classified as state secrets;

3) the principle of performance and efficiency – achievement of goals, objectives and performance indicators with the lowest possible expenditure of resources, based on an in-depth analysis of the current situation;

4) the principle of unity and integrity – unity of legislation in the field of water resources, the principles governing the organisation and functioning of the water resources management system of the Republic of Kazakhstan, and the procedure for implementing the water resources management process;

5) the principle of reliability and feasibility – a substantiated possibility of achieving the goals and performance indicators established by this Concept;

6) the principle of resource availability – identification of sources and amounts of funding, human resources, and other tangible and intangible resources required to achieve the established goals and objectives;

7) the principle of responsibility – responsibility of the executors (participants) in the process of developing the water resources management system of the Republic of Kazakhstan for ineffective or poor-quality performance of tasks and failure to achieve the expected results within their respective areas of competence, in accordance with the legislation of the Republic of Kazakhstan.

Taking into account the analysis of the current situation, international experience, the vision and the basic principles for the development of the water sector, this Concept provides for the following approaches.

1. Sustainable development of water resources

Ensuring the fulfilment of the adopted commitments to implement the Sustainable Development Goals in the area of efficient and rational use of water resources.

2. Integrated management

Coordinated management of all aspects of water resources, including their use, protection, distribution and safeguarding, taking into account environmental, social and economic factors.

3. Ecosystem approach

Strengthening interagency coordination in water resources management.

4. Adaptive management

Ensuring a prompt response to changing conditions and risks in the field of water use and protection of the water fund in order to manage water resources effectively, taking into account their dynamics and uncertainty, as well as adopting appropriate measures to minimise possible negative consequences.

5. Effective international partnership

Resolution of issues concerning the use of transboundary rivers within the framework of both bilateral and multilateral cooperation mechanisms.

These approaches may be combined and adapted depending on specific needs and changes in internal and external conditions.

The implementation of the approaches envisaged for the development of the water sector will be carried out in the following areas:

1) improving the efficiency of water resource use;

2) modernisation and development of water management infrastructure;

3) improving the information and analytical support of the water resources management system;

4) improving the environmental situation and adapting to climate change;

5) developing transboundary cooperation;

6) improving scientific, methodological and human resource support;

7) improving the institutional environment and legislative framework.

5.1. Improving the Efficiency of Water Resource Use

1. Redistribution of water resources across the country's territory

Conducting a study on the possibility of redistributing groundwater resources (Kokzhide, Aishuak and North Aishuak) to provide water to regions with insufficient water resources.

Conducting research to develop promising options for the territorial redistribution of water resources, including those of the Ertis River.

2. Rational Water Use Policy

Developing large-scale educational programmes for the population aimed at raising awareness of the importance of careful treatment of water resources and methods of their conservation.

Cooperation with international organisations to exchange experience and introduce the world's best practices in the field of water conservation.

Developing circulating and water reuse systems.

Increasing the share of treated wastewater used for secondary purposes (irrigation of agricultural land, technical water supply for industrial facilities, maintenance of urban green spaces, etc.).

3. Water Conservation in Agriculture

Compiling a list of the best available water-saving irrigation technologies and publishing it on the website of the authorised body for practical use.

Introducing advanced water-saving irrigation technologies in accordance with the list, covering up to 150,000 hectares per year.

Increasing the total area of irrigated land to 2.5 million hectares, including through the use of water-saving technologies.

Organising training programmes for agricultural producers aimed at encouraging and familiarising them with modern irrigation methods, water resources management and their efficient use.

Establishing regulations and standards for the rational use of water resources in agriculture and industry, while considering the possibility of strengthening oversight of compliance with them and introducing penalties for inefficient use of resources.

5.2. Modernisation and Development of Water Management Infrastructure

1. Construction and Modernisation of Water Management Infrastructure Facilities

Construction of 42 reservoirs.

Reconstruction of 37 reservoirs.

Modernisation and digitalisation of at least 3,500 km of irrigation canals.

Inventory of livestock watering facilities on pasture lands.

Reconstruction and construction of livestock watering facilities on pasture lands.

Reconstruction and repair and restoration works on 14,450 kilometres of irrigation canals.

Reconstruction and modernisation of the Kanysh Satpayev Canal.

Conducting studies to assess the justification and economic feasibility of, and select an acceptable project for, supplying water to the capital of Kazakhstan, including the creation of a backup source of drinking water.

Improving the level of material and technical equipment of the Kazvodkhoz Republican State Enterprise with the Right of Economic Management.

Assessing the activities of the Kazvodkhoz Republican State Enterprise with the Right of Economic Management in order to optimise non-core areas and expand other types of activities aimed at improving the efficiency of water resource use (development of recreational areas), as well as involving materials and biomass obtained incidentally during the operation of water management facilities in economic circulation.

Conducting an analysis to identify areas suitable for laying concrete lining on existing irrigation systems.

2. Expanding the Coverage of Water Management Systems and Structures Subject to Comprehensive Inspections

Conducting comprehensive inspections of 1,502 hydraulic structures, including taking into account the preparation of declarations of their safety.

In order to strengthen control over the technical condition of water management systems and structures, the issue of amending the standard forms of fishery management agreements will be considered by adding clauses obliging tenants to properly maintain the leased water bodies during the flood period.

3. Monitoring and Assessment of the Condition of Irrigated Lands

Conducting an assessment of the land reclamation condition of irrigated lands.

Expanding the network of observation wells for monitoring and assessing the land reclamation condition of irrigated lands and improving their material and technical equipment.

5.3. Improving the Information and Analytical Support of the Water Resources Management System

1. Development of Digital Technologies in Water Resource Accounting and Monitoring

Creating a unified system for accounting, monitoring and forecasting water resources, which includes information on the condition and quantity of water resources, water management and hydraulic structures, as part of the development of an interactive geoinformation platform for the water resources of the Republic of Kazakhstan, hydro.gov.kz.

Digitalisation and automation of water accounting on main and inter-farm irrigation canals, as well as the processes of accounting, control and monitoring of water resources at hydraulic structures.

Developing the digital geoservice flood.gharysh.kz for flood modelling and forecasting.

Developing the HydroSpace digital water consumption platform based on Earth remote sensing data and field verification.

Developing electronic maps (diagrams) showing the movement of floodwaters and risks to populated areas.

2. Automation of the Control and Management of Hydraulic Structures

Developing digital twins of hydraulic structures (HS) to represent their structure and characteristics, which will improve the processes of monitoring and managing these facilities.

Carrying out comprehensive digitalisation of the hydrogeological sector through the introduction of an automated groundwater monitoring system and the creation of a geographic information system (hereinafter referred to as GIS), which will make it possible to continuously monitor groundwater levels and movement, as well as increase the efficiency of their management.

Assessing and monitoring water availability in terms of groundwater resources and reserves in administrative regions and districts for household and drinking water supply to populated areas, industrial and technical water supply to industrial enterprises, irrigation of agricultural lands, and watering of pastures used for transhumant livestock farming.

3. Expansion of the Network of Hydrological Stations

Construction of new hydrological stations and creation of high-altitude snow measurement routes, followed by the integration of all information on state hydrological monitoring into the water resources information and analytical centre.

5.4. Improving the Environmental Situation and Adapting to Climate Change

1. Adaptation and Mitigation of the Consequences of Climate Change, Including Floods, High Water Events and Droughts

Conducting research to develop an environmental and economic mechanism for the distribution of water resources as part of adaptation to climate change.

Elimination or conservation of abandoned flowing hydrogeological wells. At the same time, these works will be carried out after determining whether the wells can be used for economic purposes (drinking water supply, oasis irrigation systems, pasture watering, transhumant livestock farming and others).

Analysing the effectiveness of diagnostic procedures within the existing system for early forecasting and warning of floods and droughts, as well as individual techniques and new materials that improve the effectiveness of protective structures.

Reviewing the policy on flood and drought management, including the responsibilities, rights and powers of government bodies at all levels, in order to prevent emergencies.

Developing and adopting roadmaps for the restoration of flood protection water management infrastructure (embankment dams, drainage canals, small reservoirs, basin irrigation systems, artificial basins, bank protection structures and other facilities).

2. Introduction of Innovative Approaches to Water Resource Distribution Management

Developing new approaches to the distribution of water resources in irrigation systems with the involvement of the public, agricultural water consumers and other stakeholders within the framework of basin councils.

Developing mechanisms for determining environmental flows depending on the water availability of a particular year and the intra-annual distribution of river runoff, as well as other parameters necessary for the preservation of ecosystems.

3. Improving the Environmental Situation and Water Quality of Water Bodies

Cleaning water bodies.

Implementing a set of measures to restore the Northern Aral Sea.

Taking measures to preserve the Kokaral Dam and restore the delta of the Syr Darya River.

Conducting a comprehensive study of the Caspian Sea.

Maintaining the level of Lake Balkhash at 341 m according to the Baltic Height System.

Carrying out environmental water releases.

Promoting river rehabilitation.

Conducting an inventory of sources of pollution of water bodies.

5.5. Development of Transboundary Cooperation

For the purpose of further developing transboundary cooperation, the existing bilateral and multilateral treaty framework with neighbouring states on the joint use and protection of transboundary watercourses will be improved.

1. Revision of Existing Agreements on Transboundary Water Resources

Developing and coordinating draft agreements on transboundary water bodies with China and Uzbekistan.

Developing and coordinating a draft Agreement on the Establishment of a Mechanism for Water and Energy Cooperation in Central Asia (Kazakhstan, Kyrgyzstan, Tajikistan, Turkmenistan and Uzbekistan) for the rational use of water and energy resources in the Aral Sea region.

2. Improving the Competencies of Officials

Improving the competencies of members of negotiating groups on the use and protection of transboundary water bodies.

5.6. Improving Scientific, Methodological and Human Resource Support

1. Introduction of Advanced Technologies and New Methods Taking into Account International Experience and Development of Domestic Scientific Schools

Conducting research on underground storage and accumulation of floodwaters for their subsequent use in the economy.

Conducting research to assess the management of surface water resources, taking into account adaptation to climate change and anthropogenic pressures.

Conducting research to assess the potential and prospects for the use of geothermal waters in the Almaty Region.

Modernising the material and technical facilities of the Kazakh Research Institute of Water Management LLP.

2. Strengthening Human Resource Capacity in the Water Sector through the Transfer of Training Methodologies and Knowledge for Water Sector Specialists

Improving the level of staffing at the Kazvodkhoz Republican State Enterprise with the Right of Economic Management, including through the continuous professional development of specialists with secondary education and skilled workers.

Updating educational and training programmes, taking into account new professional standards, the atlas of new professions for the water sector and innovative teaching methods.

Taking measures to develop double-degree and joint educational programmes in the water sector with foreign partner universities (including the establishment of their branches in Kazakhstan).

Intensifying the work of the Sectoral Council on Professional Qualifications in the field of use and protection of the water fund. By 2026, 11 existing professional standards for training personnel in the water sector will be updated and 9 new professional standards will be developed, with their subsequent updating every three years.

Updating technical and vocational, and post-secondary education programmes for training personnel for the water resources sector, taking into account labour market needs, professional standards and regional labour market demand maps.

5.7. Improving the Institutional Environment and Legislative Framework

1. Updating Schemes for the Integrated Use and Protection of Water Resources

Updating general and basin schemes for the integrated use and protection of water resources, taking into account hydrological, climatic and demographic forecasts.

2. A Set of Measures to Eliminate the "Black Market" in Water:

Developing and implementing clear legislative mechanisms for state control over unauthorised water use and tightening liability for violations in the field of water resource protection and use.

3. Reforming the Water Management System:

Introducing modern technologies for water resources management, including automation and digitalisation, in particular through the establishment of a water resources information and analytical centre under the Ministry of Water Resources and Irrigation.

Section 6. Target Indicators and Expected Results

6.1. Target Indicators

The successful implementation of this Concept will be characterised by the achievement of the following target indicators by the end of 2030:

Download

No.Target indicatorUnit of measurement2024202520262027202820292030
1Savings in irrigation water through the introduction of water-saving technologies in irrigated agriculturemillion m³/year32672811001428172119752192
2Increase in the reuse of water in economic sectors (increase from 17 to 28%)%--1722242628
3Level of water losses in agriculture through water conveyance canals (reduction from 50 to 25%)%50474339353025
4Volume of additionally accumulated waterkm³0.010.010.21.22.62.62.6
5Number of hydraulic structures that have undergone comprehensive inspectionsunits8210515166153472473
6Coverage of agricultural irrigated lands by hydrogeological and land reclamation monitoringthousand hectares-1921.01945.41969.81994.22018.62043.0
7Coverage of the water management system by digital technologies (increase to 40% by 2030)%-51016243240
8Number of hydrological stations, including those on transboundary riversunits377377377387399409419
9Volume of inflow into Lake Balkhash (at least 12 km³/year)km³/year12121212121212
10Volume of the Northern Aral Sea (increase from 20 to 27 km³)km³2020.621.222232527
11Level of pressure on water resources, including:        
11.1in the Aral-Syr Darya River Basin (reduction from 57.2 to 53.2%);%57.257.256.756.255.254.253.2
11.2in the Shu-Talas River Basin (reduction from 56.8 to 52.8%); 56.856.856.355.854.853.852.8
11.3in the Nura-Sarysu River Basin (reduction from 87.5 to 83.5%) 87.587.587.186.685.684.583.5
12Reduction in the number of abandoned flowing hydrogeological wells (reduction from 2,256 to 2,000 units)units--22562216215620862000
13Professional development of members of negotiating groups on the use and protection of transboundary water bodiespersons/year-555555
14Professional development of specialists with secondary education and skilled workerspersons/year450400400400400400400

6.2. Expected Results

The implementation of this Concept will make it possible to achieve the following positive changes:

1. Provision of the population and sectors of the national economy with water resources – 100%.

2. Minimisation of the negative consequences of hazardous hydrological events (high water events, floods and droughts).

3. Preservation and restoration of water bodies to a condition that ensures environmentally favourable living conditions.

The measures for implementing the Concept will be carried out in accordance with the Action Plan for the Implementation of the Concept for the Development of the Water Resources Management System of the Republic of Kazakhstan for 2024–2030, pursuant to the Appendix to this Concept.

 Appendix to the Concept for the Development of the Water Resources Management System of the Republic of Kazakhstan for 2024–2030

Action Plan for the Implementation of the Concept for the Development of the Water Resources Management System of the Republic of Kazakhstan for 2024–2030

Download

No.Name of the Main MeasuresForm of CompletionCompletion DeadlineResponsible Implementing Parties

 

 

Constitution Law Code Standard Decree Order Decision Resolution Lawyer Almaty Lawyer Legal service Legal advice Civil Criminal Administrative cases Disputes Defense Arbitration Law Company Kazakhstan Law Firm Court Cases Declaration Decree Order Resolution Decision Report Conclusion Statement Conclusion Convention Contract Memorandum Methodology Norms Note Rules Program Charter Charter Article Commentary Resolution Regulations Protocol Draft Program Rules Messages