On approval of the Rules for the organization of the customer's activities and Functions
Order of the Acting Minister of Industry and Construction of the Republic of Kazakhstan dated June 24, 2026 No. 330. Registered with the Ministry of Justice of the Republic of Kazakhstan on June 25, 2026 No. 39081
In accordance with subparagraph 26) of Article 24 of the Building Code of the Republic of Kazakhstan, I ORDER:
1. Approve:
1) Rules for the organization of the customer's activities and functions, in accordance with Appendix 1 to this order;
2) A list of certain orders that have become invalid, in accordance with Appendix 2 to this order.
2. The Committee on Construction and Housing and Communal Services of the Ministry of Industry and Construction of the Republic of Kazakhstan, in accordance with the procedure established by law, shall ensure:
1) the state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;
2) posting of this order on the Internet resource of the Ministry of Industry and Construction of the Republic of Kazakhstan after its official publication.
3. Control over the execution of this order is entrusted to the supervising Vice Minister of Industry and Construction of the Republic of Kazakhstan.
4. This order will enter into force on July 1, 2026 and is subject to official publication.
Acting Minister of Industry and Construction of the Republic of Kazakhstan
R. Isakulov
"APPROVED" by the Ministry of National Economy of the Republic of Kazakhstan
Appendix 1 to the Order of the Acting Minister of Industry and Construction of the Republic of Kazakhstan on June 24, 2026 No. 330
Rules for the organization of the customer's activities and functions
Chapter 1. General provisions
1. These Rules for the Organization of the customer's Activities and Functions (hereinafter referred to as the Rules) have been developed in accordance with subparagraph 26) of Article 24 of the Construction Code of the Republic of Kazakhstan (hereinafter referred to as the Code) and determine the procedure for organizing the customer's activities and functions.
The individual provisions of the customer when performing design and construction work are determined by agreement of the parties.
When organizing the construction of facilities by attracting money from individuals and (or) legal entities to participate in construction, the functions of the customer are regulated by the Law of the Republic of Kazakhstan "On Equity Participation in Housing Construction".
2. The following concepts are used in these Rules:
1) a digital system for organizing construction based on the "one-stop shop" principle (hereinafter referred to as the CA) is a digital system integrated with a portal designed to automate operations related to maintaining construction documentation and monitoring facilities under construction in electronic form;
2) a project is an idea of individuals and legal entities to ensure the necessary living and living conditions for humans, presented in the form of architectural, urban planning and construction documentation (drawings, graphic and text materials, engineering and estimates), including a feasibility study for construction, and (or) design estimates, disclosing the essence of the idea and the possibility of its practical implementation;
3) project documentation – a set of text and graphic documents created during the design process, which includes:
landscaping and landscaping projects. Landscaping and landscaping projects can be part of a construction project.;
urban planning projects are projects containing solutions for integrated urban planning of the organization, development and development of territories and settlements or their parts (general scheme of organization of the territory of the Republic of Kazakhstan, interregional schemes of territorial development, integrated schemes of urban planning of territories, general plans of settlements (schemes of development and development of settlements), detailed planning projects);
construction project – design and estimate documentation containing the relevant provisions of the Code, as well as estimates for the organization and management of construction, engineering preparation of the territory, landscaping. Construction projects also include projects for the conservation and postutilization of construction sites.;
An architectural project is a project for the construction of a building object (monument), in the design of which the participation of an architect is required.;
4) project management is an engineering service for the organization, planning, coordination, and control of the design, construction, and commissioning of construction facilities, which may include technical supervision and author support;
5) investor - a natural or legal person who invests his own, borrowed or borrowed funds in the form of investments;
6) contractor – an individual or legal entity licensed for the relevant type of activity, performing contract work in the field of construction under a contract or public procurement agreement concluded with the customer or with a person providing engineering services in the field of architectural, urban planning and construction activities for project management (hereinafter referred to as project management engineering services);
7) the customer is an individual or a legal entity operating in accordance with the legislation of the Republic of Kazakhstan. Depending on the objectives of the activity, the customer may be the investor of the project (program), the customer (owner) or their authorized persons.
3. The scope of the customer's activity includes the construction of new and (or) modification (expansion, modernization, technical re-equipment, reconstruction, restoration, major repairs) of existing facilities (buildings, structures and their complexes, communications), installation (dismantling), commissioning of related technological and engineering equipment, acceptance of completed facilities, termination of construction and conservation of construction of unfinished facilities.
4. The customer carries out the construction of facilities, including the implementation of investment projects (programs) at the expense of funds coming from the republican and local budgets, own funds, funds of the investor (investors), as well as from legal entities and individuals who make investments in the order of equity participation in construction.
5. The customer, on the terms defined in the contract with the investor, disposes of the investor's monetary and material resources allocated for the construction of the facility and ensures:
1) targeted and timely use of the investor's resources;
2) compliance with regulatory legal acts and regulatory technical documents during the design and construction of the facility;
3) making effective design decisions, the quality of materials, structures, equipment used, and carrying out construction and installation work;
4) compliance with the deadlines for the commissioning of the facility.
6. In the presence of the necessary permits and licenses for the relevant type of activity, the customer carries out the construction of the facility on its own, combining the functions of the customer and the contractor.
7. If necessary, the customer engages, on a contractual basis, a person providing engineering services for project management.
8. During the organization and management of construction, the following functions are performed by the customer independently:
1) making a decision on the volume of allocation of investments and the directions of their use;
2) making a decision on the beginning, suspension, conservation, termination of the construction of the facility;
3) approval of the design assignment;
4) commissioning of the constructed facility and approval of the acceptance certificate of the facility;
5) signing of documents for payment made through the treasury system.
9. The customer ensures registration of engineering survey materials (topographic survey of urban development projects, topographic survey at the design stage and executive geodetic survey at the stage of acceptance of the construction site into operation) in the automated digital system of the state urban cadastre.
Chapter 2. The procedure for organizing the activities and performing the functions of the customer
Paragraph 1. Planning of investment projects
10. When planning budget investment projects, the Customer carries out in accordance with the Budget Code of the Republic of Kazakhstan and the Rules for Planning and Implementing State Investment Projects, developing or adjusting, conducting necessary examinations of the investment proposal, feasibility studies, financial and economic studies, determining the appropriateness of budget lending, forming a portfolio of state investment projects, as well as adjustments to approved (clarified) parameters, selection, monitoring and evaluation of the implementation of state investment projects approved by the Order of the Acting Minister of National Economy of the Republic of Kazakhstan on June 28, 2025 No. 59 (hereinafter referred to as the Rules for Planning and Implementing State Investment Projects), preparation of:
investment proposals substantiating the feasibility of implementing investment projects within the framework of state, sectoral and territorial development programs;
concession offers;
feasibility studies, financial and economic studies, investment studies.
11. When planning investment projects for the construction of new technically complex production facilities and the construction of linear structures for engineering or transport infrastructure with an investment volume of over one hundred million monthly calculation indices for which there are no analog facilities in the territory of the Republic of Kazakhstan, the customer coordinates with the authorized state body responsible for managing the relevant industry before approving the design assignment., an indicator of the investment value of a unit of capacity of the projected facility.
The provisions of this paragraph do not apply to space infrastructure facilities, including facilities for ensuring their safety and engineering and technical fortification.
12. Customer:
1) independently or with the involvement of third-party specialists, draw up a task for the design of the planned facility.
The assignment for the design of technically complex production facilities and linear construction indicates the indicator of the investment value of a unit of capacity, agreed with the authorized state body responsible for the management of the relevant industry.
During the design process, when correcting and clarifying the previously approved terms of reference for the development of a feasibility study and design assignment, the indicator of the investment value of a unit of capacity is not subject to change, except in cases caused by changes in the tax legislation of the Republic of Kazakhstan on value added tax.
For investment projects for the construction of new technically complex production facilities and linear construction, exceeding the investment value of a unit of capacity approved in the design assignment is not allowed.
In coordination with the authorized state body managing the relevant industry, it is allowed to adjust the indicator of the investment value of a unit of capacity in the event of changes in the tax legislation of the Republic of Kazakhstan on value added tax, as well as in cases of unforeseen expenses in accordance with the provisions of legislation in the field of architectural, urban planning and construction activities in the Republic of Kazakhstan, including regulatory documents on pricing and estimated standards.
The design assignment is an integral part of the contract for the execution of the order for the development of pre-design and (or) design (estimate) documentation and becomes mandatory for the parties from the moment of its approval by the customer.
The assignment for the design of facilities financed by public investments establishes a condition for the use of construction materials, equipment, products and structures of Kazakhstani origin, information about which is contained in the register of Kazakhstani commodity producers.
The design assignment establishes a condition for ensuring accessibility of persons with disabilities and other low-mobility groups of the population in accordance with the provisions of state regulatory documents in the field of architecture, urban planning and construction, approved in accordance with subparagraph 63) of Article 24 of the Code., as well as the creation of working conditions in accordance with the order of the Minister of Labor and Social Protection of the Population of the Republic of Kazakhstan dated May 26, 2023 No. 179 "On approval of workplace standards for persons with disabilities" (registered in the Register of State Registration of Regulatory Legal Acts No. 32613).
The assignment for the design of facilities financed by public investments establishes a condition for the inclusion of design (design estimates) documentation in the State Bank of Construction Projects, in accordance with paragraph 1 of Article 101 of the Code.
When developing design estimates, in the design assignment for projects for the new construction of residential buildings, engineering and transport infrastructure, public buildings and structures that do not require the development of a feasibility study and funded by public investment, the customer's condition on the estimated marginal cost of construction to the investment proposal is established.
The estimated marginal cost of construction is determined in accordance with the state regulatory document on pricing in construction and is the limit of funds for the implementation of an investment project.
During the design process, the design assignment is adjusted and clarified on behalf of the customer, except for the estimated marginal cost of construction, which is the total (marginal) limit of the customer's funds for the implementation of projects. The estimated cost of construction obtained during the development of the design (design and estimate) documentation should not exceed the estimated marginal cost of construction for the investment proposal, fixed in the approved design assignment. If, at the initiative of the customer, amendments are made to the design assignment that require reworking of the developed sections of the pre-design or design (design estimate) documentation, an additional agreement to the contract is concluded, taking into account the amount of work performed.
The design assignment states that the design of facilities within the airfield area is carried out in accordance with the Rules for Issuing Permits for Activities that may pose a Threat to Aircraft Flight Safety, approved by Resolution No. 504 of the Government of the Republic of Kazakhstan dated May 12, 2011.;
2) in accordance with the Law of the Republic of Kazakhstan "On Public Procurement" (hereinafter referred to as the Law), selects organizations to carry out survey and (or) design work, and, if necessary, research, development and technological work, except in cases where the customer is funded by non-governmental investments, and concludes agreements with them;
3) provides the design organization (general designer) with a title document for the land plot, initial materials for the development of construction projects (architectural and planning assignment, vertical planning marks, copying from the detailed layout project, typical transverse profiles of roads and streets, technical specifications, schemes of routes of external engineering networks) or reconstruction (redevelopment, re-equipment) the decision for reconstruction (redevelopment, re-equipment) of premises (separate parts) of existing buildings and structures related to changes in load-bearing and enclosing structures, engineering systems and equipment, architectural and planning specifications, technical specifications and schemes of routes of external engineering networks (when submitting a questionnaire and topographic survey by the applicant), provided for by the Rules for the organization of development and passage of licensing procedures in the field of construction, approved by the authorized body for architecture, urban planning and construction, in accordance with subparagraph 25) of Article 24 of the Code;
4) in the cases provided for in subparagraph 2) According to paragraph 1 of Article 7 of the Law, the customer organizes and conducts separate tenders for the development and examination of construction projects.
The customer of projects that are subject to a comprehensive non-departmental expertise, but are not related to the state monopoly and are not the subject of public procurement, chooses any expert organization to conduct the expertise at his discretion.;
5) provides design (estimate) documentation for conducting a comprehensive non-departmental examination.
A positive conclusion of a comprehensive non-departmental expert examination is the basis for:
approval of design (estimate) documentation for the construction and modification (reconstruction, expansion, technical re-equipment, modernization, overhaul) of facilities and their complexes, laying of engineering and transport communications, engineering preparation of the territory, landscaping and landscaping, as well as the start of construction and installation work on the project;
6) ensures that the project organization eliminates the expert opinion;
7) accepts from the general designer the final version of the pre-design or design estimates in electronic format;
8) replaces construction materials, equipment, products and structures of Kazakhstani origin with imported manufacturers in agreement with the developer of the design and estimate documentation, subject to compliance with technical specifications and not exceeding cost indicators in accordance with the design and estimate documentation in the case of suspended (liquidated), missing production facilities or if the volume of production does not cover the necessary need for goods, works and services with written confirmation from Kazakhstani producers that there is no possibility of delivery within the time required for construction according to the approved work plan. At the same time, the customer applies to Kazakhstani commodity producers with a corresponding request, sent by registered mail with a notification of its delivery, by e-mail or using other means of communication that ensure the fixation of the sent request, for facilities with a construction period, modernization, reconstruction of which:
does not exceed 6 (six) months - no later than 30 (thirty) calendar days from the date of entry into force of the contract;
from 6 (six) months to 1 (one) year - no later than 45 (forty-five) calendar days from the effective date of the contract;
over 1 (one) year - no later than 60 (sixty) calendar days from the effective date of the contract.
The time limit for providing written confirmation by a Kazakhstani commodity producer is 5 (five) business days from the date of the customer's (contractor's) request. If the Kazakh producer fails to provide written confirmation on time, the customer (contractor) makes a replacement without appropriate confirmation. At the same time, a protocol is drawn up, approved by the customer, signed by the contractor, author's supervision and technical supervision.;
9) replaces building materials, equipment, products and structures of Kazakhstani origin in agreement with the developer of the design and estimate documentation for another Kazakhstani producer, subject to compliance with technical specifications, without exceeding cost indicators in accordance with the design and estimate documentation and the register of Kazakhstani producers. At the same time, a protocol is drawn up, approved by the customer, signed by the contractor, author's supervision and technical supervision.;
10) replaces building materials, equipment, products and structures in agreement with the developer of design estimates from an imported producer to a Kazakhstani producer, subject to compliance with technical specifications, without exceeding cost indicators in accordance with the design estimates and the register of Kazakhstani producers. At the same time, a protocol is drawn up, approved by the customer, signed by the contractor, author's supervision and technical supervision.;
11) determines in the consolidated estimates for the preparation (development) of the construction site and the commissioning of the facility, the amount of funds required for the preparation (development) of the construction site and the commissioning of the facility, which are not subject to indication in the design and estimate documentation, in accordance with Annex 1 to these Rules.
Paragraph 2. Organization of construction and development of the construction site
13. The customer during the organization of construction and preparation of the construction site:
1) prior to the start of construction and installation work, send a notification on the start of construction and installation work to the body carrying out state architectural and construction control and supervision in accordance with the procedure established by Article 46 of the Law of the Republic of Kazakhstan "On Permits and Notifications" (hereinafter referred to as the Law "On Permits and Notifications").
When submitting a notification of the start of construction and installation work, the company has the right to submit a schedule for visiting the construction site for the construction period through a portal and digital systems for organizing construction on a one-stop-shop basis;
2) receives the permits of the relevant organizations for:
production of works in the area of overhead power lines and communication lines, in the right-of-way of railways, in places of passage of underground utilities, in areas of mining of land plots located on the construction site;
temporary use of electricity, gas, water, steam from existing sources during construction in cities and other settlements in accordance with the construction project in case the customer does not have their own gas, water, steam and energy supply facilities for construction.;
deforestation and tree transplanting;
3) ensures coordination of land management, excavation, construction, land reclamation, and economic works on the territory of places of interest, as well as in areas of protection of the historical and cultural heritage site;
4) creates a geodetic base for the construction of the facility;
5) selects a contractor to perform construction and installation work in accordance with the Law, except in cases where the customer is funded by non-governmental investments.
The deadlines for the execution of works in the contract are determined by the calendar plan of construction and installation works included in the construction organization project (hereinafter referred to as the PIC), which has been reviewed as part of the design (design estimate) documentation and is an integral part of the contract, as well as the schedule for financing construction and installation works linked to the calendar plan. At the same time, the initial and final deadlines for the completion of work are indicated, as well as the deadlines for completing individual stages of work (interim deadlines). The composition of the main documents developed in the PIC is given in Appendix 2 to these Rules.;
6) concludes contracts for the implementation of author support and technical supervision.
If there are certified specialists in the staff, technical supervision is carried out by the customer independently.;
7) for the construction, reconstruction and capital repairs of highways, take measures to conduct an expert examination of the quality of works and materials by a person under the jurisdiction of the authorized state body for highways, which is entrusted with the functions of conducting an expert examination of the quality of works and materials, and managing road assets;
8) transfers it to the contractor in accordance with the established procedure:
within the time limits agreed with him, the title document for the land plot and the permits received from the relevant organizations in accordance with subparagraphs 2) and 3) of this paragraph;
as part of the geodetic reference base: a construction grid, red lines, main reference axes defining the dimensions of buildings (structures), high-rise reference points, main axes of engineering communications, highways, power supply lines, communications, water supply lines, sewerage, heating, gasification, issued acceptance certificate geodetic reference base for construction;
approved design and estimate documentation and other documents required for construction, regulated by regulatory technical documents on the organization of construction production.
At the same time, the contractor, on its own or with the involvement of a specialized organization, develops a project for the production of works (hereinafter referred to as the PPR). The composition of the main documents developed in the PPR is given in Appendix 3 to these Rules. The PPR is being developed for the construction of the facility as a whole, and consists of projects for certain types of work.;
9) ensures publication on the official Internet resource of the approved summary statement of the needs of basic building materials, equipment, products and structures provided for in the design (design and estimate) documentation, after receiving a positive conclusion from a comprehensive non-departmental expertise on projects implemented through public investment in construction within the framework of state and government programs.;
10) carries out control over the general management of construction, in compliance with the calendar plan, work schedules and interaction with local executive authorities on the construction of the facility;
11) at facilities financed by public investments, monitors the contractor's use of construction materials, equipment, products and structures of Kazakhstani origin included in the register of Kazakhstani commodity producers;
12) in the cases and in accordance with the procedure stipulated by the contract, transfers to the contractor the buildings and structures necessary for carrying out the work.;
13) regulates disagreements with construction participants that arise during the conclusion and execution of construction contracts;
14) visits the facility under construction, gets acquainted with the necessary executive technical documentation;
15) controls the contractor's provision:
to implement and operate an access control and management system at the construction site, which provides for the identification of persons located at the facility using biometric authentication technologies, including face recognition or other means of reliable identification;
according to the functioning of the system with the ability to record attendance, delimit access rights, and record all entrances and exits to the facility.
The information generated by the system is subject to integration with the portal of the construction organization on the principle of "one window" with the provision of centralized access, storage and data processing.;
16) carries out control:
on the Contractor's organization of a video surveillance system at the construction site using stationary cameras covering key areas of the facility;
by conducting regular monitoring of the territory by the Contractor using unmanned aerial vehicles (drones) equipped with photo and video recording equipment.
The data obtained should be processed using artificial intelligence technologies to analyze the progress of construction, identify deviations from design decisions, and monitor compliance with industrial safety and labor protection standards.
The information generated by the system is subject to integration with the portal of the construction organization on the principle of "one window" with the provision of centralized access, storage and data processing.;
17) through the organization of author's support and technical supervision, controls the quality and safety of the types of work performed that comply with the provisions established in state regulatory documents, design estimates, and comply with the terms of the contract;
18) requires the contractor to comply with the instructions of the author's support and technical supervision, and takes measures against the contractor for non-fulfillment or untimely and substandard execution;
19) ensures the fulfillment of the regulations of the state architectural and construction control and supervision bodies;
20) suspends the production of works when they are carried out with a deviation from the design (design estimates) documentation and regulations, as well as from the terms of the concluded construction contract.;
21) requires the contractor to fulfill the terms of the construction contract and eliminate defects and deviations from the design (design and estimate) documentation free of charge when performing construction work.;
22) considers proposals and, in agreement with the developer of the design and estimate documentation, makes decisions on making changes to the approved design and estimate documentation of a non-fundamental nature that do not affect the structural scheme of the facility, its spatial planning, engineering, technical or technological design solutions and approved technical and economic indicators, with subsequent registration and delivery for storage.
At the same time, for projects being built at the expense of budgetary funds and other forms of public investment, the cost of non-fundamental changes does not exceed 30% of the total estimated cost.;
23) takes measures to recover penalties (fines, penalties) from the contractor for non-fulfillment or improper fulfillment of contractual obligations.
Paragraph 3. Financing, accounting and reporting
14. The customer in the field of financing, accounting and reporting:
1) ensures acceptance and payment for the work actually performed, within the time limits and in accordance with the procedure established by legislative acts or the contract.
If the contractor's actual costs are less than those that were taken into account when determining the price (making estimates and a transport scheme for the delivery of building materials, products and structures), the customer pays for the work performed at the price stipulated in the contract, except in the case when the design and estimate documentation was prepared by the contractor independently or by his order.
In the case when the customer has several different sources of financing for facilities, the cost estimates are agreed with each investor in accordance with the proportions of funds spent, in accordance with the amount of financing for each investor.;
2) verifies the volume of work performed, the validity of prices, as well as information contained in documents submitted by contractors, suppliers and other organizations for payment for work (services) performed by them, products supplied and other costs incurred, without interfering with the operational and economic activities of the contractor.
Decides to increase or decrease the cost of the work performed based on the relevant proposals of the contractor, technical supervision and author's support.
At the same time, an increase in the estimated cost of construction for budgetary investment projects in connection with the adjustment of design estimates is carried out in accordance with the procedure established by the Rules for Planning and Implementing Public Investment Projects.;
3) monitors the targeted and effective use of budgetary funds;
4) organizes and maintains accounting and statistical records, as well as signs:
certificates of completed works in accordance with Appendix 4 to these Rules;
certificates of completed works in accordance with Appendix 5 to these Rules;
a certificate of the cost of construction work performed and costs (according to the basic index method) in accordance with Appendix 6 to these Rules.;
a certificate of the cost of construction work performed and costs (according to the resource method) in accordance with Appendix 7 to these Rules.
The procedure and deadlines for acceptance of completed works and payments for completed construction and installation work during construction are established by a contract agreement between the parties based on a catalog of contractual (unit) prices and monthly payments for them are made in accordance with the forms agreed between the customer and the contractor.
When forming a catalog of contractual (single) prices, calculations between the customer and the contractor for completed construction, installation and repair work may be carried out according to structural elements (percentage of technical readiness of these elements), according to individual stages stipulated by the contract, or after completion of all work under the contract.
At the same time, the creation of a catalog of contractual (single) prices, acceptance of completed works, and calculations fully ensure the fulfillment of the customer's functions in the field of financing, accounting, and reporting.
During the construction of the facility at the expense of non-governmental investments, monthly payments for completed construction and installation work are made in accordance with the forms agreed between the customer and the contractor.
Paragraph 4. Acceptance of completed facilities, termination of construction and conservation of unfinished facilities
15. After completing all construction and installation works at the facility, landscaping, provision of equipment and inventory in full accordance with the approved project (design and estimate documentation), the contractor (general contractor) notifies the customer of the facility's readiness for delivery.
16. The commissioning of a highway construction, reconstruction and overhaul facility is carried out by the customer in the presence of a final report on the quality of works and materials issued by the National Center for Quality of Road Assets, in accordance with the procedure established by the Rules for Organizing the Examination of the Quality of Works and Materials of Highways by the National Center for Quality of Road Assets, approved by the Order of the Minister of Investments and Development of the Republic of Kazakhstan dated March 20, 2015 No. 305 (registered in the Register of State Registration of Regulatory Legal Acts No. 11523).
17. The customer, who has received a written notification from the contractor (general contractor) about the readiness of the facility for commissioning, and a set of executive documentation executed in electronic form in the CA during the implementation of projects financed by public investments, as well as at all housing and civil facilities, in accordance with these Rules, carries out the acceptance of the facility into operation..
In order to put the facility into operation, the customer:
1) organizes a comprehensive check of the facility's readiness;
2) determines the operating mode of the facility during testing and acceptance;
3) if necessary, ensures the organization and commissioning of the facility;
4) requests from the contractor, persons carrying out technical supervision and author's support, signed conclusions on the quality of construction and installation works, agreed with the local executive body of the capital, region and city of republican significance, carrying out state architectural and construction control and supervision, in the form of conclusions on the quality of construction and installation works and the conformity of the work performed with the project declaration of conformity approved by the authorized body for Architecture, Urban Planning and Construction, in accordance with subparagraph 74) of Article 24 of the Code;
signed conclusion on the compliance of the facility with fire safety standards of the territorial body of the authorized body in the field of civil protection;
5) on the basis of a declaration of conformity, an opinion on the quality of construction and installation works, agreed with the local executive body of the capital, the region and the city of republican significance, which carries out state architectural and construction control and supervision, an opinion on the conformity of the work performed with the project, an opinion on the conformity of the object with fire safety standards, together with the contractor, technical supervision and author support, verifies the executive technical documentation executed in electronic form in the CA during the implementation of projects, financed by public investments, as well as at all housing and civil facilities in accordance with these Rules, for availability and completeness (including engineering and geodetic surveys (executive survey), examines and puts the facility into operation in the form of an act of acceptance of the construction site into operation, approved by the authorized body for construction architecture, urban planning and construction, in accordance with subparagraph 73) of Article 24 of the Code.
The act of acceptance of the constructed construction object into operation is signed by the customer, the contractor (general contractor), the persons carrying out technical supervision and author's support on the basis of the documents specified in subparagraph 4) of this paragraph.
The commissioning of a constructed construction facility is carried out by the owner (customer, investor, developer) independently in the cases provided for in Article 133 of the Code and the Acceptance Rules, as well as the forms of the certificate of acceptance of the construction facility by the customer (owner, investor) independently, approved by Order of the Minister of Industry and Construction of the Republic of Kazakhstan dated March 20, 2026 No. 123 (it is registered in the Register of State registration of regulatory legal acts for No. 38184).
6) If violations of approved design decisions and state (interstate) standards are detected, as well as if there are negative conclusions, the facility is put into operation after the contractor (general contractor) has eliminated the violations.
Upon receipt of the conclusion of the author's support and (or) technical supervision on the unsuitability of the facility for operation or poor–quality performance of construction and installation work, the customer applies to the relevant government authorities to hold the construction participants responsible for the violation, and also takes measures in accordance with the Code of Administrative Offenses of the Republic of Kazakhstan for improper performance of contractual obligations.;
7) approves the certificate of acceptance of the facility into operation.
The date of signing the acceptance certificate is considered to be the date of its approval and the date of commissioning of the facility.
From the day the facility is put into operation, the costs associated with the maintenance of the facility are borne by the customer.;
8) within 3 (three) business days from the date of approval of the act of acceptance of the facility into operation, sends to the non-profit joint stock Company State Corporation "Government for Citizens" at the location of the facility the approved act of acceptance of the facility into operation, accompanied by the technical characteristics of the facility, executive geodetic survey of the actual position of engineering networks and (or) buildings (structures) and documents provided for in subparagraph 4) of this paragraph;
9) the local executive body (the customer), within 10 (ten) business days, signs an act of acceptance and transfer of engineering networks and structures built at the expense of public investment after registration with the Government for Citizens State Corporation and sends it to the operating organization.
The absence of the possibility of connecting networks built according to the project to backbone or distribution networks due to circumstances beyond the control of the Customer (the absence of previously designed, but not built or not commissioned networks to which connection is planned) is not the reason for the refusal to sign the transmission acceptance certificate by the operating organization;
10) the operating organization, within 10 (ten) working days from the date of receipt from the local executive body of the act of acceptance of the transfer, draws up an inspection report of engineering networks and structures. If the operating organization has any comments, the Customer eliminates them within 15 working days from the date of their receipt. When drawing up an inspection report, the operating organization issues comments once, if network and equipment malfunctions are detected, as well as if their design estimates do not match.
If the comments are not eliminated within the time period established by this paragraph, it is extended until the comments are completely eliminated, which is notified to the local executive body within 2 (two) business days.
A second appeal to the operating organization is carried out after the complete elimination of the comments issued by the operating organization. The reason for refusing to issue an inspection report is a malfunction of the networks (equipment). When drawing up and signing the Inspection Report, comments not related to the malfunction of networks (equipment), including additional ones not included in the list of initial comments, are not issued. The inspection report is signed by the operating organization after the removal of the comments by the owner (customer) of engineering networks and structures within 2 (two) business days.;
11) the operating organization shall draw up an inspection report within 2 (two) business days after the Customer has eliminated the comments, and within 5 (five) business days after signing the inspection report on the identified comments, it shall sign the acceptance certificate and the inspection report, and send them to the local executive body.;
12) the local executive body, within 10 (ten) working days from the date of receipt of the act of acceptance of the transfer and the act of inspection, makes an appropriate decision on engineering networks and structures into communal ownership and approves the act of acceptance of the transfer, after which it sends the decision and the act of acceptance to the operating organization, which, within 5 working days from the date of receipt of the documents, includes engineering networks and structures in the list of serviced facilities;
13) for external engineering networks and structures built at the expense of private funds, the owner (customer), in order to transfer property to the receiving party, applies to the operating organization with an application with the relevant documents attached according to the design and estimate documentation;
14) the operating organization, within 1 (one) business day after receiving the documents, checks them for completeness, and, if there are any comments, notifies the owner thereof. The owner (customer) of engineering networks and structures within 3 (three) business days eliminates the comments and provides the missing documents to the operating organization.;
15) taking into account the completeness of the accepted documents, the operating organization, within 10 (ten) working days from the date of receipt of the documents, draws up an act of technical inspection of the transmitted outdoor networks and structures.;
16) if the operating organization has any comments during the preparation of the technical inspection report, the owner (customer) of engineering networks and structures eliminates them within 8 (eight) working days from the date of their receipt. The reason for refusing to issue a technical inspection report is a malfunction of the networks (equipment), while the operating organization issues reasoned comments once. Comments that are not related to a malfunction of networks (equipment), including additional ones that are not included in the list of initial comments and in the design documentation, are not issued. The technical inspection report is signed by the operating organization after the removal of the comments by the owner (customer) of engineering networks and structures within 2 (two) business days.;
17) the operating organization, within 1 (one) business day after signing the technical inspection report, sends it along with the documents to the local executive body.;
18) the local executive body, within 10 (ten) working days from the date of receipt of the documents from the operating organization, decides on the admission of engineering networks and structures to communal ownership.;
19) the local executive body, within 5 (five) business days after the conclusion of the contract, approves the act of acceptance of the transfer of engineering networks and structures, signed by the owner (customer) of engineering networks and structures and agreed with the operating organization, and also sends the act of acceptance of the transfer and the contract to the operating organization, and the owner (customer) of engineering networks provides the operating organization with access to engineering networks and facilities;
20) the operating organization shall draw up an inspection report within 2 (two) business days after the Customer has eliminated the comments and, within 5 (five) business days after signing the inspection report, sign the acceptance and transfer certificate and send it and the inspection report to the local executive body;
21) the local executive body, within 10 (ten) working days from the date of receipt of the act of acceptance of the transfer and the act of inspection, makes an appropriate decision on engineering networks and structures into communal ownership and approves the act of acceptance of the transfer, after which it sends the decision and the act of acceptance to the operating organization, which within 5 (five) working days from the date of receipt of documents includes engineering networks and structures in the list of serviced facilities;
22) for external engineering networks and structures built at the expense of private funds, the owner (customer), in order to transfer property to the receiving party, applies to the operating organization with an application with the relevant documents attached according to the design and estimate documentation;
23) the operating organization, within 1 (one) business day after receiving the documents, checks them for completeness, and, if there are any comments, notifies the owner thereof. The owner (customer) of engineering networks and structures, within 3 (three) business days from the date of receipt of the notification, eliminates the comments and provides the missing documents to the operating organization.;
24) taking into account the completeness of the documents, the operating organization shall, within 10 (ten) working days from the date of receipt of the documents, draw up a technical inspection report on the transmitted outdoor networks and facilities;
25) if the operating organization has any comments when drawing up a technical inspection report, the owner (customer) of engineering networks and structures eliminates them within 8 (eight) working days from the date of their receipt. The reason for refusing to issue a technical inspection report is a malfunction of the networks (equipment), while the operating organization issues reasoned comments once. Comments that are not related to a malfunction of networks (equipment), including additional ones that are not included in the list of initial comments, will not be issued. The technical inspection report is signed by the operating organization after the removal of the comments by the owner (customer) of engineering networks and structures within 2 (two) business days.;
26) the operating organization, within 1 (one) business day after signing the technical inspection report, sends it along with the documents to the local executive body.;
27) the local executive body, within 10 (ten) working days from the date of receipt of the documents from the operating organization, decides on the admission of engineering networks and structures to communal ownership.;
28) the local executive body, within 5 (five) business days after the conclusion of the contract, approves the act of acceptance of the transfer of engineering networks and structures, signed by the owner (customer) of engineering networks and structures and agreed with the operating organization, and also sends the act of acceptance of the transfer and the contract to the operating organization, and the owner (customer) of engineering networks and structures facilities provide the operating organization with access to engineering networks and facilities.
29) in case of involvement of an individual entrepreneur or a legal entity in order to ensure the safe operation of a construction facility on the basis of a contract for the operation of a construction facility, the owner of the construction facility or persons who own it on another legal basis, transfer to this person the following documents:
engineering survey results;
copies of the design and estimate documentation certified by the design organization, which received a positive conclusion from a comprehensive non-departmental expert examination of construction projects.;
copies of the positive conclusion of the comprehensive non-departmental expert examination of construction projects and all its adjustments;
copies of executive technical documentation;
a copy of the certificate of acceptance of the construction site into operation with mandatory appendices;
a copy of the title document for the land plot;
passports of technological equipment;
other documentation necessary for the safe operation of the construction site.
18. In case of a decision to terminate (suspend) the construction and conservation of the facility, the customer:
1) on the basis of the results of the technical inspection, the act accepts an unfinished object from the contractor and ensures the development of a conservation project;
2) approves the estimate for the performance of conservation work and, through the organization of author support, monitors their quality performance;
3) before starting work on the conservation of an unfinished object, send a notification to the body carrying out state architectural and construction control and supervision, in accordance with the procedure established by Article 46 of the Law on Permits and Notifications;
4) during the period of conservation, organizes the protection of material assets at an unfinished facility.
19. During the warranty period of operation of the facility, the customer participates jointly with the contractor and the operating organization in the inspection of the facility and ensures that the contractor eliminates or at its expense the identified defects, except in cases where the malfunctions were caused by improper operation.
Paragraph 5. Interaction of the customer with the person providing engineering services for project management
20. A person providing engineering services for project management is engaged by the customer or investor for the entire investment period, including the pre-design stage and the stages of design, construction and commissioning of an object or several objects, or at any stage of the project implementation.
21. When implementing a project being built at the expense of public investments, it is not allowed to combine project management functions and contract work (development of pre-design, design and estimate documentation and (or) construction and installation work) in this project.
22. If there are certified specialists on staff, the person providing engineering services for project management independently carries out technical supervision and/or engages certified specialists for this purpose.
23. A person providing engineering services for project management performs the functions established by the Rules for the Provision of Engineering Services in the field of architectural, urban planning and construction activities, approved by the authorized body for Architecture, Urban Planning and Construction, in accordance with paragraph 2 of Article 59 of the Code.
24. Payment for engineering services in the field of architectural, urban planning and construction activities is made in proportion to the cost of the completed volumes of work on the construction of facilities.
For facilities under construction with the participation of public investments, the costs of attracting engineering services are paid within the limits stipulated in the design and estimate documentation for the construction of facilities, approved in accordance with state regulatory documents in the field of architecture, urban planning and construction.
In case of adjustment of the design and estimate documentation for the construction of facilities without changing the design decisions, the price of the previously concluded contract for the provision of engineering services in the field of architectural, urban planning and construction activities is not subject to increase.
Appendix 1 to the Rules of organization of the customer's activities and functions
Form
Customer _______________________________________________________( name of the organization)
The consolidated estimate for the preparation (development) of the construction site and the commissioning of the facility has been "APPROVED" in the amount of ______________ thousands of tenge including:value added tax ______________ thousands of tenge_______________________________________________________________( link to the approval document, its date and number)Summary estimate for the preparation (development) of the construction site and the commissioning of the facility _____________________________________________________(name of the organization, building, structure)
Compiled in prices as of 20 __.
Download
The number is in order
Estimates and calculations numbers
Name of costs
Estimated cost, thousand tenge
1
2
3
4
Head of the organization ___________________ _____________( position, signature) (last name, first name, patronymic (if any)Place of printing (if available)
Appendix 2 to the Rules of organization of the customer's activities and functions
The composition of the main documents being developed in the construction organization project
1. A calendar (object) construction plan, which defines the time and order of construction of the main and auxiliary buildings and structures, the distribution of capital investments and the volume of construction and installation work.
2. The construction master plan, which indicates the location of permanent and temporary buildings and structures, roads, utility networks, places of connection of temporary utilities to existing networks, indicating sources of electricity, water, heat, steam, as well as the location of storage sites, main cranes and other mechanized installations, signs of fixing the center networks, buildings and structures.
In cases where organizational and technical solutions cover the territory adjacent to the construction site, then, in addition to the construction master plan, a situational plan is developed, which indicates enterprises of the material and technical base, quarries, residential settlements, external routes and roads (indicating their length and capacity), railways, junction stations, marine, river berths, communication lines, electrical lines, deforestation, and other available facilities.
3. Organizational and technological schemes that determine the optimal sequence of construction of buildings and structures.
4. The list of volumes of the main construction and installation and special works.
5. A statement of the need for building structures, products, materials and equipment, linked in time to the graphical part of the calendar (object) plan, indicating the codes of the main building resources from the classifier of building resources, approved in accordance with the Rules for the Development and Approval of Elements of National Reference Information, approved by the order of the Chairman of the Agency for Strategic Planning and Reforms of the Republic of Kazakhstan dated 26 September 2024, No. 77 and from the general classifier of goods, works and services.
6. A schedule of the need for basic construction machinery and vehicles, linked in time to the graphical part of the calendar (object) plan.
7. Schedule the need for construction personnel, linked in time to the graphic part of the calendar (object) plan.
8. An explanatory note, which, along with a description of the construction conditions, substantiates the methods of production and combining work, including those performed in winter conditions with seasonal shift work. Measures are envisaged to protect labor and preserve the natural environment. The needs for basic construction machinery and mechanisms, vehicles, electricity, steam, water, oxygen, and compressed air are substantiated.
The need for human resources, housing, social and cultural services, and the duration of construction is substantiated.
The following technical and economic indicators are given in the construction organization project:
total duration of construction (in months), including the preparatory period and the equipment installation period;
maximum number of employees;
labor costs for construction and installation work (person-days) included in the labor cost statement according to the consolidated standards, on the basis of which the estimated part of the object calendar plan is compiled.
The composition and content of the construction organization project is supplemented taking into account the complexity of the construction of the facility, depending on the spatial planning and design solutions in accordance with the current regulatory documents on the preparation of the construction organization project.
Appendix 3 to the Rules of organization of the customer's activities and functions
The composition of the main documents being developed in the work project
1. Technological schemes of workplace organization.
2. Occupational safety and health solutions, fire safety measures in accordance with the provisions of current regulatory technical documents.
3. Measures for the performance of work by the method of end-to-end in-line team work.
4. Measures to carry out shift work, if necessary.
5. Solutions for laying temporary engineering and communication networks, including emergency lighting.
6. A list of technological equipment and mounting equipment, as well as cargo slinging schemes.
7. An explanatory note, which, along with justifications for decisions on the production of works, including those performed in winter, provides the need for energy resources and solutions to cover it, a list of all temporary, mobile inventory buildings, structures and devices, measures to ensure the safety of materials and structures.
Measures to protect existing and under construction facilities from damage are also given (skipping spring floods, uneven thawing with the onset of a period of positive temperatures, certain types of work performed in winter).
8. Technical and economic indicators, including the volume and duration of construction and installation work, the level of mechanization and labor costs per 1 cubic meter (m3) of building area, per unit of physical volume of work, or another indicator adopted for labor productivity.
Appendix 4 to the Rules of organization of the customer's activities and functions
Form
Customer: ____________________________________________________________(full name, business identification number or individual identification number, address, communication data)Contractor: __________________________________________________________(full name, business identification number or individual identification number, address, communication information)Construction site: ____________________________________________________________(name, address)An object: _____________________________________________________________(name,)Work agreement (contract) no. ______ from _____________
The act of completed work. ______________ ( month, year) on __________________________ works
Footing:Compiled in the prices of 20__ year
Download
Number
The code and the position number of the standard
Name of work and costs, unit of measurement
Quantity
Unit cost, tenge
Total cost, tenge
Overhead costs, tenge
Labor costs, person-hour, construction workers,workers servicing machines
Country of origin
in order
according to the estimate
Total, including salaries of construction workers
operation of machines, including wages of machinists
Total, including salaries of construction workers
operation of machines, including wages of machinists
per unit
in total
1
2
3
4
5
6
7
8
9
10
11
12
13
Total direct costs including cost:materials, products and structures of equipment, other costs, overhead costs, payroll, labor intensity, non-standard and unforeseen costs, based on the base prices of 20__:Estimated salary and standard labor intensity of the employee at current prices:Taxes, fees, mandatory paymentsother:Value added tax:Total:
Download
Passed (Contractor)
Accepted (by the Customer)
__________________________________(name of the organization, business identification number, or individual identification number)
________________________________(name of the organization, business identification number, or individual identification number)
(position, signature, transcript of signature)Place of printing (if available)
(position, signature, transcript of signature)Place of printing (if available)
Place of printing (if available)Technical Supervision Specialist(s):___________________________________________________________(position, surname, first name, patronymic (if any), individual identification number, certificate number, signature)Place of printing (if available)The developers of the construction project or the specialist(s) of the author's support_______________________________________________________________( position, surname, first name, patronymic (if any), individual identification number, certificate or order number, signature)
Note:
1. The form is used for certificates of completed works, compiled according to estimates using the basic index method.
2. Column 13 indicates information on those material resources and equipment that are accounted for in a separate line in the act of completed work.
Appendix 5 to the Rules of organization of activity and implementation of the customer's function
Form
Customer: ____________________________________________________________(full name, business identification number or individual identification number, address, communication information)Contractor: __________________________________________________________(full name, business identification number or individual identification number, address, data on communication facilities)Construction site: ____________________________________________________________(name, address)An object: _____________________________________________________________(name)Work agreement (contract) no. ______ from _____________
The act of completed work. ______________ ( month, year) on __________________________ works
Basis: Compiled in prices for 20___ year, tenge
Download
The number is in order
Item number of the local estimate
The cipher of the standard position, the resource code
Naming of works and costs
Unit of measurement
Quantity
The cost of the unit of measurement, tenge
Total cost, tenge
Country of origin
1
2
3
4
5
6
7
8
9
Passed (Contractor)
Accepted (by the Customer)
_______________________________(name of the organization, business identification number, or individual identification number)
_________________________________(name of the organization, business identification number, or individual identification number)
(position, signature, transcript of signature)Place of printing (if available)
(position, signature, transcript of signature)Place of printing (if available)
Total according to the act: ___________________________________________________ Place of printing (if available)Technical Supervision Specialist(s): _______________________________( position, surname, first name, patronymic (if any), individual identification number, certificate number, signature)Place of printing (if available)The developers of the construction project or the specialist(s) of the author's support:_______________________________________________________________(position, surname, first name, patronymic (if any), individual, identification number, certificate or order number, signature)
Note:
1. The form is used for certificates of completed works, drawn up according to estimates using the resource method.
2. Column 9 indicates information on those material resources and equipment that are accounted for in a separate line in the act of completed work.
Statement of material resources and equipment according to the Act of completed work ____________________________________________________(name of the building, structure, facility, construction site)
Footing: The act of completed works __________________
Download
No., Number in order
Resource codes
Naming of resources
Unit of measurement
Quantity
Product origin (country of origin)
CT-KZ certificate (if available)
1
2
3
4
5
6
7
Materials (in ranked order)Equipment (in ranked order)
Appendix 6 to the Rules of organization of the customer's activities and functions
Form
Customer:Contractor:The name of the building and its address:
Certificate of the cost of completed construction works and costs (according to the basic index method)
for _____ 20___ years
Download
Code
Code
Contract
Source of funding
Organizational and legal form
the customer
the contractor
Number
date
name
code
name
code
Name of launch complexes and facilities
The cost of work performed and expenses in thousands of tenge
Value added tax
Total to be paid
from the beginning of the year to the reporting month, inclusive of value added tax
in the reporting month (for __) without value added tax
from column 1
Construction and installation works at the estimated base price level of 20__
of these
The cost of other expenses not included in the construction and installation works in the estimated base price level of 20 __
additional costs
in the reporting month
installation of equipment
for the purchase of materials
other additional costs
But
1
2
3
4
5
6
7
8
9
10
Place of printing (if available)Customer _______________________________________________________( position, surname, first name, patronymic (if any), signature, business identification number or individual identification number)Place of printing (if available)Contractor _____________________________________________________( position last name, first name, patronymic (if any), signature, business identification number or individual identification number)Place of printing (if available)Technical Supervision Specialist(s):______________________________________________________________(position, surname, first name, patronymic (if any), individual identification number, certificate number, signature)
Appendix 7 to the Rules of organization of the customer's activities and functions
Form
Customer:Contractor:The name of the building and its address:
Certificate of the cost of completed construction works and costs (according to the resource method)for __________ 20___ year
Download
Business identification number/Individual identification number
The classifier of the organizational and legal form
Contract
Source of funding
the customer
the contractor
the customer
the contractor
Number
date
Name of the program (subprograms, specifics)
code
Name of launch complexes and facilities
Cost of work performed and costs, tenge
Value added tax
in total
from the beginning of construction to the reporting month inclusive
from the beginning of the year to the reporting month inclusive
in the reporting month, without value added tax
of these:
Construction and installation works
Equipment, furniture and inventory
Other expenses
But
1
2
3
4
5
6
7
8
Place of printing (if available)Customer _______________________________________________________( position, surname, first name, patronymic (if any), signature, business identification number or individual identification number, seal)Place of printing (if available)Contractor _____________________________________________________( position last name, first name, middle name (if any), signature, business identification number or individual identification number, seal)Place of printing (if available)Technical Supervision Specialist(s): ______________________________( position last name, first name, patronymic (if any), signature, business identification number or individual identification number,certificate number, signature, seal)
_____________________________________________________(position, surname, first name, patronymic (if any), signature, business identification number or individual identification number, seal)Place of printing (if available)Technical Supervision Specialist(s): ______________________________( position, surname, first name, patronymic (if any), signature, business identification number or individual identification number,certificate number, signature, seal)
Appendix 2 to the Order of the Acting Minister of Industry and Construction of the Republic of Kazakhstan on June 24, 2026 No. 330
List of expired orders
1. Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for organizing the activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 10795).
2. Subparagraph 2) of paragraph 1 of the Order of the Minister of Investment and Development of the Republic of Kazakhstan dated April 29, 2017 No. 255 "On Amendments to Certain Orders of the Minister of National Economy of the Republic of Kazakhstan" (registered in the Register of State Registration of Regulatory Legal Acts No. 15196).
3. Order of the Minister of Investment and Development of the Republic of Kazakhstan dated December 8, 2017 No. 854 "On Amendments to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 16132).
4. Item 1 of the List of certain Orders of the Minister of National Economy of the Republic of Kazakhstan, which are amended and supplemented by the Order of the Minister of Investment and Development of the Republic of Kazakhstan dated February 26, 2018 No. 135 "On Amendments and additions to certain Orders of the Minister of National Economy of the Republic of Kazakhstan" (registered in the Register of State Registration of Regulatory Legal Acts No. 16499).
5. Order of the Minister of Investment and Development of the Republic of Kazakhstan dated May 4, 2018 No. 308 "On Amendments to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 16943).
6. Order of the Minister of Investment and Development of the Republic of Kazakhstan dated September 19, 2018 No. 656 "On Amendments and Additions to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 17420).
7. Order of the Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated April 2, 2019 No. 178 "On Amendments to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 18476).
8. Order of the Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated July 2, 2019 No. 470 "On Amendments to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 18967).
9. Paragraph 1 of the Order of the Acting Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated March 17, 2020 No. 142 "On Amendments and Additions to Certain Orders of the Minister of National Economy of the Republic of Kazakhstan" (registered in the Register of State Registration of Regulatory Legal Acts No. 20169).
10. Order of the Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated October 2, 2020 No. 513 "On Amendments to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 21369).
11. Order of the Acting Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated November 3, 2020 No. 590 "On Amendments to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 21605).
12. Subparagraph 1) of paragraph 1 of the Order of the Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated April 23, 2021 No. 189 "On Amendments to Certain Orders of the Minister of National Economy of the Republic of Kazakhstan" (registered in the Register of State Registration of Regulatory Legal Acts No. 22623).
13. Paragraph 2 of the Order of the Acting Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated August 5, 2021 No. 420 "On Amendments to Certain Orders of the Minister of National Economy of the Republic of Kazakhstan" (registered in the Register of State Registration of Regulatory Legal Acts No. 23902).
14. Subparagraph 1) of paragraph 1 of the Order of the Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated November 11, 2022 No. 625 "On Amendments and Additions to certain Orders of the Ministry of National Economy of the Republic of Kazakhstan" (registered in the Register of State Registration of Regulatory Legal Acts No. 30589).
15. Item 2 of the List of certain orders that are amended and supplemented by the Order of the Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated December 30, 2022 No. 762 "On Amendments and Additions to certain Orders" (registered in the Register of State Registration of Regulatory Legal Acts No. 31542).
16. Item 1 of the List of certain Orders of the Ministry of National Economy of the Republic of Kazakhstan, which are amended and supplemented by the Order of the Acting Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated May 29, 2023 No. 392 "On Amendments and additions to certain Orders of the Ministry of National Economy of the Republic of Kazakhstan" (registered in the Register of State Registration of Regulatory Legal Acts No. 32623).
17. Subparagraph 1) of paragraph 1 of the Order of the Acting Minister of Industry and Construction of the Republic of Kazakhstan dated September 13, 2023 No. 3 "On Amendments and Additions to Certain Orders of the Minister of National Economy of the Republic of Kazakhstan" (registered in the Register of State Registration of Regulatory Legal Acts No. 33432).
18. Order of the Minister of Industry and Construction of the Republic of Kazakhstan dated December 1, 2023 No. 102 "On Amendments and Additions to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 33722).
19. Item 1 of the List of certain orders of the Ministry of National Economy of the Republic of Kazakhstan, which are amended by the Order of the Minister of Industry and Construction of the Republic of Kazakhstan dated December 28, 2023 No. 171 "On Amendments to certain Orders of the Minister of National Economy of the Republic of Kazakhstan" (registered in the Register of State Registration of Regulatory Legal Acts No. 33841).
20. Order of the Minister of Industry and Construction of the Republic of Kazakhstan dated May 13, 2024 No. 169 "On Amendments to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 34381).
21. Paragraph 2 of the Order of the Acting Minister of Industry and Construction of the Republic of Kazakhstan dated July 19, 2024 No. 269 "On Amendments and Additions to the Order of the Minister of National Economy of the Republic of Kazakhstan dated February 3, 2015 No. 71 "On Approval of the Rules for the Provision of Engineering Services in the field of architectural, urban Planning and construction activities" and the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On approval of the Rules for organizing activities and performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 34775).
22. Order of the Acting Minister of Industry and Construction of the Republic of Kazakhstan dated September 26, 2024 No. 336 "On Amendments and Additions to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 35133).
23. Order of the Minister of Industry and Construction of the Republic of Kazakhstan dated March 31, 2025 No. 107 "On Amendments to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 35914).
24. Order of the Minister of Industry and Construction of the Republic of Kazakhstan dated May 16, 2025 No. 167 "On Amendments to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 36129).
25. Paragraph 1 of the Order of the Minister of Industry and Construction of the Republic of Kazakhstan dated June 27, 2025 No. 232 "On Amendments to Orders of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" and November 20, 2015 No. 707 "On Approval of the Rules determining the cost of construction of facilities at the expense of public investments and funds from quasi-public sector entities" (registered in the Register of State Registration of Regulatory Legal Acts No. 36367).
26. Item 1 of the List of certain orders of the Ministry of National Economy of the Republic of Kazakhstan, which are amended and supplemented by the Order of the Minister of Industry and Construction of the Republic of Kazakhstan dated July 17, 2025 No. 266 "On Amendments and additions to certain Orders of the Ministry of National Economy of the Republic of Kazakhstan" (registered in the Register of State Registration of Regulatory Legal Acts No. 36474).
27. Item 2 of the List of certain orders of the Minister of National Economy of the Republic of Kazakhstan, which are amended by the Order of the Minister of Industry and Construction of the Republic of Kazakhstan dated September 2, 2025 No. 341 "On Amendments to certain Orders of the Minister of National Economy of the Republic of Kazakhstan" (registered in the Register of State Registration of Regulatory Legal Acts No. 36808).
28. Order of the Minister of Industry and Construction of the Republic of Kazakhstan dated October 30, 2025 No. 465 "On Amendments and Additions to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 37300).
29. Order of the Minister of Industry and Construction of the Republic of Kazakhstan dated April 10, 2026 No. 159 "On Amendments to the Order of the Minister of National Economy of the Republic of Kazakhstan dated March 19, 2015 No. 229 "On Approval of the Rules for Organizing Activities and Performing the Functions of the Customer (Developer)" (registered in the Register of State Registration of Regulatory Legal Acts No. 38463).
Constitution Law Code Standard Decree Order Decision Resolution Lawyer Almaty Lawyer Legal service Legal advice Civil Criminal Administrative cases Disputes Defense Arbitration Law Company Kazakhstan Law Firm Court Cases Declaration Decree Order Resolution Decision Report Conclusion Statement Conclusion Convention Contract Memorandum Methodology Norms Note Rules Program Charter Charter Article Commentary Resolution Regulations Protocol Draft Program Rules Messages