Article 75. The procedure for the acceptance of facilities into operation of the Law on Architectural, Urban Planning and Construction Activities in the Republic of Kazakhstan

АMANAT партиясы және Заң және Құқық адвокаттық кеңсесінің серіктестігі аясында елге тегін заң көмегі көрсетілді

Article 75. The procedure for the acceptance of facilities into operation of the Law on Architectural, Urban Planning and Construction Activities in the Republic of Kazakhstan

     1. The acceptance of the object from the contractor (general contractor) is carried out by the customer in conjunction with technical and copyright supervision.

     2. After receiving a written notification from the contractor (general contractor) on the readiness of the facility for commissioning, the customer accepts the facility for operation.

     3. From the date of receipt of the notification from the contractor (general contractor) on the readiness of the facility, the customer requests from the contractor (general contractor) and persons carrying out technical and design supervision and fire inspection, a declaration of conformity, conclusions on the quality of construction and installation work, compliance of the work performed with the project and compliance of the facility with fire safety requirements.

     The contractor (general contractor) and persons carrying out technical and design supervision, within three working days from the date of receipt of the request from the customer, submit a declaration of conformity, conclusions on the quality of construction and installation work and compliance of the work performed with the project, or negative conclusions.

     The conclusion of the author's supervision on the conformity of the work performed with the project is the basis for providing providers of engineering and utility services with access to their services in accordance with previously issued technical specifications for the design of the facility, if this does not contradict the current norms and rules.

  The territorial body of the authorized body in the field of civil protection, within the time limits established by the legislation of the Republic of Kazakhstan, from the date of receipt of the application from the customer, carries out a fire technical inspection and, if the facility meets the mass presence of people and buildings with a height of more than twenty-eight meters, issues an appropriate conclusion before their commissioning.

     4. The customer, on the basis of a declaration of conformity, conclusions on the quality of construction and installation work, compliance of the work performed with the project and compliance of the facility with fire safety requirements, together with the contractor (general contractor), persons carrying out technical and design supervision, is obliged to check the executive technical documentation for availability and completeness, inspect and put the facility into operation. according to the relevant act (to conduct a final inspection of the facility for readiness for commissioning).

     5. In case of violations of approved design decisions and state (interstate) standards, as well as in the presence of negative conclusions, the customer accepts the facility for operation after the contractor (general contractor) has eliminated the violations.

     When the identified violations are eliminated, the facility is put into operation in accordance with the procedure established by this article.

     6. Providing the customer with design (design and estimate) documentation, declarations of conformity, conclusions on the quality of construction and installation work, compliance of the work performed with the project and compliance of the facility with fire safety requirements does not relieve the contractors for design and construction and installation work, persons carrying out technical and author supervision, fire and technical inspection, responsibility for the work performed during the design, construction, acceptance and commissioning of the facility.

     The footnote. Article 75 as amended by the Law of the Republic of Kazakhstan dated 29.12.2014 No. 269-V (effective from 01.01.2016); as amended by the Law of the Republic of Kazakhstan dated 24.05.2018 No. 156-VI (effective ten calendar days after the date of its first official publication).  

 

The Law of the Republic of Kazakhstan dated July 16, 2001 No. 242.

This Law regulates the relations that arise between government agencies, individuals and legal entities in the process of carrying out architectural, urban planning and construction activities in the Republic of Kazakhstan, and is aimed at creating a full-fledged human habitat and vital activity, sustainable development of settlements and interuniverse territories.

President    