Article 44. Evasion from concluding a public procurement contract of the Law on Public Procurement - Excluded by the Law of the Republic of Kazakhstan dated July 1, 2024 No. 106-VIII SAM.
1. If the potential supplier recognized as the winner has not submitted a signed public procurement contract to the customer within the time limits established by this Law or, having concluded a public procurement contract, has not provided security for the execution of the public procurement contract and (or) the amount in accordance with Article 26 of this Law (if any), then such potential supplier The supplier is deemed to have evaded the conclusion of a public procurement contract.
2. If a potential supplier identified by the winner of public procurement is found to have evaded the conclusion of a public procurement contract, the public procurement organizer withholds the security of the application for participation in the tender (auction).
The footnote. Article 44 as amended by the Law of the Republic of Kazakhstan dated December 26, 2018 No. 202-VI (effective from 01.01.2019).
The Law of the Republic of Kazakhstan dated December 4, 2015 No. 434-V SAM.
President
Republic of Kazakhstan
© 2012. RSE na PHB "Institute of Legislation and Legal Information of the Republic of Kazakhstan" of the Ministry of Justice of the Republic of Kazakhstan
Constitution Law Code Standard Decree Order Decision Resolution Lawyer Almaty Lawyer Legal service Legal advice Civil Criminal Administrative cases Disputes Defense Arbitration Law Company Kazakhstan Law Firm Court Cases